Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD08-01357
StatusFinaled
Name BRIGHTON PROPERTIES LLC
Site Address 2796 S VICTORY VIEW WAY
Project NameVIC PARK BUILDING #3
Customer Number 
ePlanReviewNo
Description
(CORPORATE EXPRESS - VIC PARK BLDG #3) Permit to construct a 5,943 square foot warehouse with office and mercantile. Work to include: [Construction of interior non-bearing partition walls to create an office, a storage room, a drivers room, a conference room, and separate sex accessible restrooms,] new doors in specified locations, install new H-VAC system including ducts and diffusers, new plumbing, new electrical, install a new steel guard rail, install a new stairwell at back of warehouse, and installation of interior finishes in compliance with chapter 8 of the IBC. This building is sprinklered for area increase any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be maintained as regulated by the fire department in accordance with NFPA 13 standards. The design, testing and utilization of industrial steel storage racks shall be in accordance with the RMI Specification for the Design, Testing and Utilization of Industrial Steel Storage Racks. Any storage racking over 8 ft. in height will require a separate permit. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/21/20088/22/20088/22/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/21/2008 at 1:47:17 PM. Contact: ###-####. ok for perm occ.
FIRE-Final Inspection8/21/20088/22/20088/22/2008APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final8/20/20088/21/20088/21/2008PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/20/2008 at 2:53:18 PM. Contact: ###-####. Life/safety failed.
FIRE-Final Inspection8/20/20088/21/20088/21/2008AFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit passed and the emergency light added in the warehouse and in the drivers room. All ofther items will be ok.
Code Occupancy Approval  8/19/2008 DONE
BLD-Other8/14/20088/15/20088/15/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/14/2008 at 4:41:51 PM. Contact: ###-####. Ceiling grid ok. All repairs done.
BLD-Other8/14/20088/14/20088/14/2008PFAIL
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/14/2008 at 8:04:40 AM. Contact: ###-####. Needs to remove screws from clip to main and cross runners, also cmplete install of clips. c/n posted.
BLD-Wall cover7/28/20087/28/20087/28/2008PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/28/2008 at 8:20:49 AM. Contact: ###-####. walls ok need backing for ada bars, mec ri