Winco Foods Distribution Center (Shell Only) - To construct a new 712,555 square foot, one story, concrete tilt-up and steel frame warehouse shell building and related site improvements. This building will contain dry goods, cooler and freezer warehouse areas, as well as, office and maintenance support areas. This building is fully fire sprinkled. The sprinklers are used for area. This building is an unlimited area building. Minimum 60 foot open yards and public ways must be maintained around this building. This permit is for a cold shell only and no occupancy is allowed under this permit. A separate tenant improvement permit is required to finish this building for occupancy. Separare permits are required to construct the other proposed accessory buildings. All construction per the approved plans and attached comment list. DRH07-00594 JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection1/13/20101/13/20101/13/2010PPASS
DetailsForrest France
Shell permit fire life safety passed.
BLD-Final1/5/20101/6/20101/6/2010APASS
DetailsForrest France
Shell permit fire life safety finaled.
BLD-Final1/5/20101/5/20101/6/2010PPASS
DetailsJim Storey
final set per angie b. isued l/c
DOC - Permit Finaled1/6/20101/6/20101/6/2010PPASS
DetailsJim Storey
FIRE-Final Inspection9/15/20099/16/20099/17/2009APART
DetailsForrest France
TOC approved.
FIRE-Alarm Testing9/15/20099/16/20099/17/2009APART
DetailsForrest France
TOC approved.
BLD-Final9/9/20099/10/20099/10/2009APART
DetailsJim Storey
George Phone #: ###-####-What needs to be done to final need all sign offs
BLD-Aging Inspection8/3/20098/3/20098/3/2009 PASS
DetailsJim Storey
FIRE-Conference6/2/20096/2/20096/3/2009PDONE
DetailsForrest France
On site conference regarding fire alarm permit work site inspection schedule and related fire sprinkler system interconnections.
FIRE-Conference5/18/20095/18/20095/18/2009PDONE
DetailsForrest France
FIRE-Conference5/13/20095/13/20095/13/2009PDONE
DetailsForrest France
Regarding on site meeting for project schedule.
BLD-Aging Inspection3/10/20093/10/20093/10/2009 PART
DetailsJim Storey
drygoods 9 line need colm fix. 2nd colm from the north wall.