BLD-Final | 7/9/2009 | 7/10/2009 | 7/10/2009 | P | PASS |
Tony Young
|
|
|
Dale Phone #: ###-#### c of o issued
|
DOC - Permit Finaled | 7/10/2009 | 7/10/2009 | 7/10/2009 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/9/2009 | 7/9/2009 | 7/9/2009 | P | NR |
Tony Young
|
|
|
Dale Phone #: ###-#### need trades, need roof finished,, on site conf only
|
BLD-Final | 7/8/2009 | 7/9/2009 | 7/9/2009 | A | NR |
Tony Young
|
|
|
Dale Phone #: ###-####
|
BLD-Grading Inspection | 7/8/2009 | 7/8/2009 | 7/8/2009 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Wall cover | 3/2/2009 | 3/3/2009 | 3/3/2009 | P | PASS |
Tony Young
|
|
|
dale Phone #: ###-####,, interior shear
|
BLD-Energy code compliance | 2/27/2009 | 3/2/2009 | 3/2/2009 | P | PART |
Tony Young
|
|
|
dale Phone #: ###-#### energy ok,, need interior shear
|
BLD-Framing/Rough-in | 2/24/2009 | 2/25/2009 | 2/26/2009 | P | PASS |
Tony Young
|
|
|
Mike Phone #: ###-####
|
BLD-Wall cover | 2/4/2009 | 2/5/2009 | 2/5/2009 | P | PART |
Tony Young
|
|
|
Mike Phone #: ###-#### got fix for 5/8missed,, ok,, exterior ok to cover
|
BLD-Other | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | FAIL |
Tony Young
|
|
|
mike Note: shear & nail Phone #: ###-#### we dont like but we take need to nail per plan, need engineer fix on wall w/out 5/8"
|
BLD-Foundation | 11/17/2008 | 11/17/2008 | 11/17/2008 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/17/2008 at 6:59:09 AM. Contact: ###-####.
|
BLD-Footing | 11/10/2008 | 11/10/2008 | 11/10/2008 | P | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### wip,, will pour on holiday,, verify stamped letter on soils,, T. R. out till 12th,, verified field report,, 90% rebar in forms
|