BLD-Final | 12/12/2008 | 12/12/2008 | 12/12/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/12/2008 at 8:51:22 AM. Contact: ###-####. All issues have been resolved. ok for perm occ.
|
BLD-Final | 12/10/2008 | 12/11/2008 | 12/11/2008 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/10/2008 at 4:33:51 PM. Contact: ###-####. Restroom sign to be posted on wall. Provide transition from wood to conc. floors at doorway to warehouse. Returns on handrail not long enough. Provide code compliant guardrail at mezz. Provide tempered glazing at hazardous locations.
|
FIRE-Final Inspection | 12/10/2008 | 12/11/2008 | 12/11/2008 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Final | 12/10/2008 | 12/10/2008 | 12/10/2008 | P | NR |
Mike Jordan
|
|
|
a.j. Phone #: ###-####
|
FIRE-Final Inspection | 12/10/2008 | 12/10/2008 | 12/10/2008 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguishers as discussed, provide doors and hardware for the two rooms under the mezzanine and move the stored items in the warehouse from infront of the rear exit door.
|
FIRE-Final Inspection | 12/5/2008 | 12/5/2008 | 12/5/2008 | P | CANC |
Troy Cobbley
|
|
|
AJ Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
|
BLD-Framing/Rough-in | 11/4/2008 | 11/4/2008 | 11/4/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/4/2008 at 10:49:06 AM. Contact: ###-####. nailing on shear walls ok. ok to cover.
|
BLD-Framing/Rough-in | 10/31/2008 | 10/31/2008 | 10/31/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/31/2008 at 9:02:05 AM. Contact: ###-####. Reviewed RFI from engineer and architect concering changeat demissing wall for studs supporting second floor TJI. All in place work was as per RFI. Will have RFI scanned into permit.
|
BLD-Framing/Rough-in | 10/27/2008 | 10/28/2008 | 10/28/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/27/2008 at 2:53:47 PM. Contact: ###-####. ok to rock interior walls and ceiling . Needs to add more 6d cooler nails for shearwalls. Contractor was notified. Will call for reiinspection when corrections have been made.
|
BLD-Framing/Rough-in | 10/24/2008 | 10/27/2008 | 10/27/2008 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/24/2008 at 10:43:54 AM. Contact: ###-####. Needs to pull mech permit and get ri insp. prior to framing insp. Contractor was notified.
|
FIRE-Conference | 10/16/2008 | 10/16/2008 | 10/16/2008 | P | DONE |
Troy Cobbley
|
|
|
I went over storage/racking permit requirements.
|
BLD-Framing/Rough-in | 9/30/2008 | 10/1/2008 | 10/1/2008 | A | PASS |
Mike Jordan
|
|
|
mike Note: demizing wall Phone #: ###-#### Please 1/2 hr prior to inspection to meet with. Demissing wall.
|