BLD-Final | 4/8/2009 | 4/9/2009 | 4/9/2009 | A | PASS |
Tony Young
|
|
|
tiffany Phone #: ###-####
|
DOC - Permit Finaled | 4/9/2009 | 4/9/2009 | 4/9/2009 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 3/26/2009 | 3/27/2009 | 3/27/2009 | A | FAIL |
Tony Young
|
|
|
tiffany Phone #: ###-#### c/n,, need trades 1st
|
BLD-Energy code compliance | 1/12/2009 | 1/12/2009 | 1/12/2009 | P | PASS |
Tony Young
|
|
|
stephie Phone #: ###-####
|
BLD-Framing/Rough-in | 1/5/2009 | 1/6/2009 | 1/6/2009 | A | PART |
Tony Young
|
|
|
tiffany Phone #: ###-#### need support under overbuild rafter tails,, need plans and specs for energy inspection,, ok to insulate
|
BLD-Foundation | 10/13/2008 | 10/14/2008 | 10/14/2008 | A | PART |
Tony Young
|
|
|
tiffany Phone #: ###-#### poured
|
BLD-Footing | 10/8/2008 | 10/8/2008 | 10/8/2008 | P | PASS |
Mike Jordan
|
|
|
Fred Phone #: ###-####. TONY- I see an issue with setbacks on east side with carport on adjacent lot. Contractor that the same guy owns both lots and that he will have overhang cut back to beam on carport. I do not know if this is good enough or acceptable.
|