BLD-Final | 11/30/2009 | 11/30/2009 | 11/30/2009 | A | PASS |
Mike Jordan
|
|
|
call Jim Phone #: ###-#### Internet Inspection Request from: James Larkin
|
DOC - Permit Finaled | 11/30/2009 | 11/30/2009 | 11/30/2009 | P | PASS |
Mike Jordan
|
|
|
Cert. of occ was issued.
|
BLD-Other | 4/3/2009 | 4/3/2009 | 4/3/2009 | P | CANC |
Mike Jordan
|
|
|
Jim- building wrap Phone #: ###-####
|
BLD-Framing/Rough-in | 3/18/2009 | 3/18/2009 | 3/18/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/18/2009 at 6:21:22 AM. Contact: ###-####. Inspected remaining 5/8 type x rock in garages for 2hr. fire walls. Also verified installation of exterior water resistive barrier.
|
BLD-Energy code compliance | 3/12/2009 | 3/13/2009 | 3/13/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/12/2009 at 8:37:30 PM. Contact: ###-####. ok to rock.
|
BLD-Framing/Rough-in | 3/11/2009 | 3/11/2009 | 3/11/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/11/2009 at 7:15:27 AM. Contact: ###-####. ok to insul.
|
BLD-Energy code compliance | 3/10/2009 | 3/11/2009 | 3/11/2009 | P | CANC |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 1st. layer of 5/ 8 type x rock from ceiling to roof deck, both sides.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/20/2009 | 2/20/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/19/2009 at 9:59:51 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/19/2009 | 2/19/2009 | P | PASS |
Mike Jordan
|
|
|
jim - firewalls Phone #: ###-####. Verified firerated plywood at 4ft. laydown parapet at overbuild areas...ok.
|
BLD-Framing/Rough-in | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/18/2009 at 5:08:48 PM. Contact: ###-####. nailing for type x rock at over build areas ok.
|
BLD-Framing/Rough-in | 2/18/2009 | 2/18/2009 | 2/18/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 2nd floor, 2nd layer, both sides type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 2/17/2009 | 2/17/2009 | 2/17/2009 | P | PART |
Mike Jordan
|
|
|
Jim- Fire wall Phone #: ###-####. 2nd. floor, 1st. layer of 5/8 type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 2/11/2009 | 2/13/2009 | 2/13/2009 | P | NR |
Mike Jordan
|
|
|
jim - fire wall Phone #: ###-####
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st. floor, 2nd layer 5/8 type x rock for 2hr. wall. both sides.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st. floor, 5/8 type x rock, for 2hr. wall remaining side.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/10/2009 | 2/10/2009 | P | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st. floor, 5/8 type X rock for 2hr. wall, one side only.
|
BLD-Footing | 2/4/2009 | 2/5/2009 | 2/5/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/4/2009 at 2:52:23 PM. Contact: ###-####. Interior footings.
|
BLD-Energy code compliance | 1/23/2009 | 1/23/2009 | 1/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: 861-024. Rigid insul. at interior side of stemwall.
|
BLD-Foundation | 1/22/2009 | 1/22/2009 | 1/22/2009 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 1/21/2009 | 1/22/2009 | 1/22/2009 | A | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####. Rescheduled for pm.
|
BLD-Footing | 1/20/2009 | 1/21/2009 | 1/21/2009 | A | PASS |
Mike Jordan
|
|
|
Exterior permiter footings.
|