BLD-Final | 8/13/2009 | 8/13/2009 | 8/14/2009 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 8/14/2009 | 8/14/2009 | 8/14/2009 | P | PASS |
Mike Jordan
|
|
|
Cert. of occ. was issued.
|
BLD-Final | 8/13/2009 | 8/13/2009 | 8/13/2009 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/13/2009 at 6:08:08 AM. Still needs elec. final. Rescheduled for pm.
|
BLD-Other | 4/3/2009 | 4/3/2009 | 4/3/2009 | P | PASS |
Mike Jordan
|
|
|
Jim- building wrap Phone #: ###-####.. Verified instalation of weather resistive barrier. ok.
|
BLD-Framing/Rough-in | 3/23/2009 | 3/23/2009 | 3/23/2009 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/23/2009 at 6:14:01 AM. Contact: ###-####.
|
BLD-Energy code compliance | 3/23/2009 | 3/23/2009 | 3/23/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/23/2009 at 6:14:01 AM. Contact: ###-####. ok for cover.
|
BLD-Framing/Rough-in | 3/20/2009 | 3/20/2009 | 3/20/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/20/2009 at 7:04:20 AM. Contact: ###-####. ok to insul.
|
BLD-Framing/Rough-in | 3/9/2009 | 3/9/2009 | 3/10/2009 | P | PASS |
Mike Jordan
|
|
|
Naling for both layers of 5/8 type x rock from ceiling to underside of roof deck. Also verified fire rated plywood for laydown parapet at overbuild ares.
|
BLD-Framing/Rough-in | 3/2/2009 | 3/2/2009 | 3/2/2009 | A | PASS |
Mike Jordan
|
|
|
Attacment of 5/8 typex rock for 2hr. walls at over build areas. ok.
|
BLD-Framing/Rough-in | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2009 | 2/24/2009 | 2/24/2009 | A | CANC |
Mike Jordan
|
|
|
Jim This inspection is for the fire wall Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 2nd floor, 2nd. layer, both sides, 5/8 type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/20/2009 | 2/20/2009 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/19/2009 at 9:56:01 PM. Contact: ###-####. 2nd. floor, 1st. layer type x rock for 2hr. wall, both sides.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/19/2009 | 2/19/2009 | P | NR |
Mike Jordan
|
|
|
jim - firewalls Phone #: ###-####
|
BLD-Framing/Rough-in | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/18/2009 at 10:10:41 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/18/2009 | 2/18/2009 | 2/18/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st.floor, 2ndlayer, both sides type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 2/17/2009 | 2/17/2009 | 2/17/2009 | P | PART |
Mike Jordan
|
|
|
Jim- Fire wall Phone #: ###-####. 1st. floor, 1st. layer of type x rock for 2hr. wall, both sides.
|
BLD-Footing | 2/12/2009 | 2/12/2009 | 2/12/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/12/2009 at 7:40:38 AM. Contact: ###-####. Interior footings ok.
|
BLD-Energy code compliance | 2/2/2009 | 2/3/2009 | 2/3/2009 | A | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. Rigid foam insul. on interior side of styemwall. ok.
|
BLD-Foundation | 1/29/2009 | 1/29/2009 | 1/29/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/29/2009 at 7:38:41 AM. Contact: ###-####.
|
BLD-Foundation | 1/27/2009 | 1/28/2009 | 1/28/2009 | P | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Foundation | 1/22/2009 | 1/23/2009 | 1/23/2009 | P | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 1/20/2009 | 1/21/2009 | 1/21/2009 | A | PASS |
Mike Jordan
|
|
|
Jim-###-####. Exterior permiter footings.
|