BLD-Final | 1/6/2009 | 1/7/2009 | 1/7/2009 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/6/2009 at 9:42:51 AM. Contact: ###-####.ok for perm occ
|
FIRE-Final Inspection | 1/6/2009 | 1/6/2009 | 1/6/2009 | P | PASS |
Forrest France
|
|
|
Reinspection for correction items passed, fire life safety finaled.
|
FIRE-Final Inspection | 1/5/2009 | 1/5/2009 | 1/5/2009 | P | FAIL |
Troy Cobbley
|
|
|
Provide emergency lighting as discussed in the east side/existing open office and corridors.
|
BLD-Framing/Rough-in | 12/15/2008 | 12/15/2008 | 12/16/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/15/2008 at 8:01:16 AM. Contact: ###-####. ok to cover ceiling
|
BLD-Framing/Rough-in | 12/9/2008 | 12/10/2008 | 12/10/2008 | A | FAIL |
Dave Hannah
|
|
|
same Phone #: ###-#### ceiling grid needs to run kickers on top of walls
|
FIRE-Final Inspection | 12/5/2008 | 12/5/2008 | 12/5/2008 | A | NR |
Forrest France
|
|
|
Need project related fire sprinkler and alarm permit finals prior.
|
BLD-Framing/Rough-in | 11/24/2008 | 11/24/2008 | 11/24/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/24/2008 at 10:19:09 AM. Contact: ###-####.
|
BLD-Wall cover | 11/13/2008 | 11/13/2008 | 11/13/2008 | P | PASS |
Dave Hannah
|
|
|