BLD-Final | 1/7/2009 | 1/8/2009 | 1/8/2009 | A | PASS |
Jim Sly
|
|
|
ammon Phone #: ###-#### OK for Perm Occ.
|
BLD-Conference | 1/7/2009 | 1/7/2009 | 1/7/2009 | P | DONE |
Jim Sly
|
|
|
ammon Phone #: ###-#### Checked truss Engineering fix for additional load of HVAC equipment.
|
FIRE-Final Inspection | 1/7/2009 | 1/7/2009 | 1/7/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/6/2009 | 1/6/2009 | 1/6/2009 | P | FAIL |
Troy Cobbley
|
|
|
Provide approved hardware on the restroom doors.
|
BLD-Framing/Rough-in | 12/3/2008 | 12/4/2008 | 12/4/2008 | A | PASS |
Jim Sly
|
|
|
amon Phone #: ###-#### OK'd decorative frame above restrooms.... still need Eng. on HVAC load on trusses.
|
BLD-Framing/Rough-in | 11/26/2008 | 11/28/2008 | 11/28/2008 | A | FAIL |
Jim Sly
|
|
|
ammon Phone #: ###-####-call for access info Need Electr and Mech ..... Framing not per approved plan......does not show deck, deck cantilever, guards above restrooms. Need truss Eng to approve HVAC equip attached to trusses.
|