BLD-Final | 5/11/2009 | 5/11/2009 | 5/11/2009 | P | PASS |
Jim Sly
|
|
|
Please call one half hour upon arrival, thanks. Phone #: ###-#### Internet Inspection Request from: Darren Gossett
|
DOC - Permit Finaled | 5/11/2009 | 5/11/2009 | 5/11/2009 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 5/8/2009 | 5/11/2009 | 5/11/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 5/6/2009 | 5/7/2009 | 5/7/2009 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Darren.
|
FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 | A | PART |
Troy Cobbley
|
|
|
The six office/meeting rooms are ok to occupy. The project related fire alarm permit needs to be finaled and the ceiling tile to the north west of these six new rooms needs to be installed.
|
FIRE-Alarm Testing | 3/31/2009 | 4/1/2009 | 4/1/2009 | A | DONE |
Troy Cobbley
|
|
|
See the project related fire alarm permit for the items needing addressed.
|
FIRE-Final Inspection | 3/30/2009 | 3/31/2009 | 3/31/2009 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Internet Inspection Request from: Darren Gossett Inspection cancelled from web by: Darren Gossett
|
BLD-Other | 3/20/2009 | 3/23/2009 | 3/23/2009 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/20/2009 at 4:10:42 PM. Contact: ###-####. Grid OK
|
BLD-Final | 3/9/2009 | 3/9/2009 | 3/9/2009 | A | NR |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 2/20/2009 | 2/20/2009 | 2/20/2009 | P | PASS |
Jim Sly
|
|
|
Please call 1/2 hour before arrival Phone #: ###-#### Internet Inspection Request from: Darren Gossett Top of wall bracing...OK
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | FAIL |
Jim Sly
|
|
|
jason Phone #: ###-#### C/N Need to install bracing at top of all walls.
|