BLD-Final | 3/8/2010 | 3/9/2010 | 3/9/2010 | A | PART |
Mike Jordan
|
|
|
Cory Phone #: ###-####. All remaining firecaulking is completed. HAndrail installed. Will be ok for perm occ. once zoning has signed off perm.
|
BLD-Conference | 2/22/2010 | 2/22/2010 | 2/22/2010 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the project superintendant about the need to submit data sheets and floor plan/door locations where the delayed egress locks had been installed. These documents need to be provided to Dan Stuart.
|
BLD-Final | 2/19/2010 | 2/22/2010 | 2/22/2010 | P | PART |
Mike Jordan
|
|
|
corey Phone #: ###-####. ok for temp occ. Needs to complete firecaulking in riser room, provide handrail on some exterior stairs. Will also need to sibmit plans for delayed egress locks to plan reveiw. Noted no tenants until mid march.
|
FIRE-Final Inspection | 2/19/2010 | 2/22/2010 | 2/22/2010 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Scott's permission until the as-built fire alarm plans have been reviewed, approved and any changes inspected. When this is done the life safety can be passed. All other corrections have been completed.
|
FIRE-Final Inspection | 2/19/2010 | 2/19/2010 | 2/19/2010 | P | FAIL |
Troy Cobbley
|
|
|
See a list of corrections listed on the back of the city approved fire plan review comments. They include posting the building address, providing an additional exit discharge light from Dining 126, posting the occupant load sign in Dining 126, mounting the K class fire extinguisher....ect
|
BLD-Final | 2/12/2010 | 2/16/2010 | 2/16/2010 | A | NR |
Mike Jordan
|
|
|
Corey Phone #: ###-####. Still needs fire/life/safety and zoning. Called Corey at provided number. Will reschedule.
|
BLD-Conference | 2/8/2010 | 2/8/2010 | 2/8/2010 | P | PASS |
Mike Jordan
|
|
|
On site to check status and job progress.
|
BLD-Conference | 1/6/2010 | 1/6/2010 | 1/6/2010 | A | PASS |
Mike Jordan
|
|
|
Stop by project to check status. finish carpentry in progress. Was able to speak with Corey with CCI and discussed openings in 1hr. roof ceiling and kitchen hood penetration.
|
BLD-Conference | 12/21/2009 | 12/21/2009 | 12/21/2009 | P | PASS |
Mike Jordan
|
|
|
Called and left message for Corey to call me back regarding openings in 1hr ceiling and hood.
|
BLD-Other | 12/18/2009 | 12/18/2009 | 12/18/2009 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Other | 12/17/2009 | 12/17/2009 | 12/17/2009 | P | PASS |
Mike Jordan
|
|
|
1hr. ceiling and walls in areas 1 and 3.
|
BLD-Other | 12/16/2009 | 12/16/2009 | 12/16/2009 | A | PART |
Mike Jordan
|
|
|
1hr. ceiling and wall assemblies in areas 1 and 3.
|
BLD-Other | 12/15/2009 | 12/15/2009 | 12/15/2009 | P | PART |
Mike Jordan
|
|
|
1hr. ceilings at areas 1 and 3.
|
BLD-Other | 12/14/2009 | 12/14/2009 | 12/14/2009 | P | PART |
Mike Jordan
|
|
|
1hr ceilings for areas 1 and 3. wip.
|
BLD-Other | 12/11/2009 | 12/11/2009 | 12/11/2009 | P | PASS |
Mike Jordan
|
|
|
1hr. ceilings, corridor walls and rommseperation walls at areas 1 2,4.
|
BLD-Other | 12/11/2009 | 12/11/2009 | 12/11/2009 | A | PART |
Mike Jordan
|
|
|
1hr. ceiling, corridor walls and room seperation walls. wip. areas 1,2,3.
|
BLD-Other | 12/10/2009 | 12/10/2009 | 12/10/2009 | P | PASS |
Mike Jordan
|
|
|
area 4 ok.
|
BLD-Other | 12/10/2009 | 12/10/2009 | 12/10/2009 | A | PART |
Mike Jordan
|
|
|
5/8 type x rock for 1hr. ceilings, corridor walls and room seperation walls.
|
BLD-Other | 12/9/2009 | 12/9/2009 | 12/9/2009 | P | PART |
Mike Jordan
|
|
|
Area 1,2,and 4 1hr. lids, corridor walls and room seperation walls.
|
BLD-Other | 12/9/2009 | 12/9/2009 | 12/9/2009 | A | PART |
Mike Jordan
|
|
|
Base layers for 1r. ceiling, and corridor walls and room seperation walls. Area 1 and 4.
|
BLD-Other | 12/8/2009 | 12/8/2009 | 12/8/2009 | P | PASS |
Mike Jordan
|
|
|
Area 5 ok for cover on sheetrock. Base layer on lids in area 4 and 1.
|
BLD-Other | 12/8/2009 | 12/8/2009 | 12/8/2009 | A | PART |
Mike Jordan
|
|
|
1st and 2nd. layers of 1hr. ceiling assembly in area 4. wip.
|
BLD-Other | 12/7/2009 | 12/7/2009 | 12/7/2009 | P | PASS |
Mike Jordan
|
|
|
1hr. fire partions and corridor walls. area5. wip.
|
BLD-Other | 12/7/2009 | 12/7/2009 | 12/7/2009 | A | PASS |
Mike Jordan
|
|
|
!hr ceiling, corridor and room seperation wall assemblies in area 5.
|
BLD-Other | 12/4/2009 | 12/4/2009 | 12/4/2009 | P | PASS |
Mike Jordan
|
|
|
1st and 2nd layers of 5/8 typex rock for 1hr. ceiling
|
BLD-Other | 12/4/2009 | 12/4/2009 | 12/4/2009 | A | PASS |
Mike Jordan
|
|
|
wip on 1hr. roof/ceiling assembly at area 5. 1st and 2nd. layers.
|
BLD-Energy code compliance | 12/1/2009 | 12/1/2009 | 12/1/2009 | P | PASS |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Areas 1,2,3 and 4 are complete. Also all firecaulking is completed in siad above areas. ok to start 1st. layer of 5/8 type x at 1hr. lid after sprinkler ri has passed.
|
BLD-Energy code compliance | 11/24/2009 | 11/24/2009 | 11/24/2009 | A | PASS |
Mike Jordan
|
|
|
Area 5 only. ok.
|
BLD-Energy code compliance | 11/23/2009 | 11/23/2009 | 11/23/2009 | P | PART |
Mike Jordan
|
|
|
area 5 only. wip.
|
BLD-Framing/Rough-in | 11/20/2009 | 11/23/2009 | 11/23/2009 | A | PART |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Firestopping and blocking still in progress.
|
BLD-Framing/Rough-in | 11/20/2009 | 11/20/2009 | 11/20/2009 | P | PASS |
Mike Jordan
|
|
|
Areas 1,2,3,and 4. Still needs to complete firestopping and fireblocking. ok to start insul. on area 5 on and partial on area1 only.
|
BLD-Framing/Rough-in | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | CANC |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Inspection has been rescheduled for this afternoon.
|
BLD-Framing/Rough-in | 11/13/2009 | 11/13/2009 | 11/13/2009 | P | PART |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Framing in area 5 ok up to common area. airseal is also completed. All concelled areas have been rock at ceiling. Needs to complete firecaulk.
|
FIRE-Conference | 11/9/2009 | 11/9/2009 | 11/10/2009 | P | DONE |
Troy Cobbley
|
|
|
I stopped by this project site (11-9-09) to verify that sprinkler piping was not being covered by sheetrock and found that the fire alarm system had been installed without drawings even being submitted. I posted a stop work order for the installation of the fire alarm system and any other trades whos work would effect the fire alarm system. The fire alarm contractor was not on site so I left a voice message on the building contractors phone of the situation. The stop work order is to remain in effect until the fire alarm plans have been issued.
|
BLD-Conference | 11/9/2009 | 11/9/2009 | 11/9/2009 | P | DONE |
Mike Jordan
|
|
|
wip on arera 5 repairs. Will also needs to supply ul approved listed assembly for B vent membrane penetration at 1hr roof/ceiling assembly.
|
BLD-Conference | 11/5/2009 | 11/6/2009 | 11/6/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 11/5/2009 | 11/6/2009 | 11/6/2009 | P | PART |
Mike Jordan
|
|
|
wip on resolveing issues in area 5 only.
|
BLD-Framing/Rough-in | 11/5/2009 | 11/5/2009 | 11/5/2009 | P | PART |
Mike Jordan
|
|
|
corey Phone #: ###-####. Framing for area 5 only. Needs to complete firecaulking, nail off all hangars and straps.
|
BLD-Framing/Rough-in | 10/30/2009 | 10/30/2009 | 10/30/2009 | P | PART |
Mike Jordan
|
|
|
corey - partial Phone #: ###-####. Strapping on roofs in areas 3,4 and 5. Alsorecieved rfi from engineer regarding the use of staples in leiu of nails. ok. Will have scaned into permit.
|
BLD-Framing/Rough-in | 10/26/2009 | 10/27/2009 | 10/27/2009 | A | PART |
Mike Jordan
|
|
|
corey - partial Phone #: ###-####. Drag truss connections in areas 1 and 2 ok as per RFI from engineer. Will have RFI scanned into permit.
|
BLD-Framing/Rough-in | 10/22/2009 | 10/22/2009 | 10/22/2009 | A | PART |
Mike Jordan
|
|
|
Still need RFI from engineer of record for staples on roof in leiu of nails.
|
BLD-Framing/Rough-in | 10/14/2009 | 10/15/2009 | 10/15/2009 | A | PART |
Mike Jordan
|
|
|
corey Phone #: ###-####. Inspected shear on roof deck for drag trusses. Straps on underneath side not yet installed. Also noted remainder of roof was stapled down. Will need rfi from engineer for use of staples. Drag trusses were nailed as per approved plans.
|
BLD-Conference | 10/6/2009 | 10/6/2009 | 10/6/2009 | A | PART |
Mike Jordan
|
|
|
Received paper work from enginner of record regarding shear wall strapping in area 4. Letter states that the installed straps are sufficient for the lateral overturning loads. Will have letter scanned into permit.
|
BLD-Framing/Rough-in | 9/28/2009 | 9/29/2009 | 9/29/2009 | A | PART |
Mike Jordan
|
|
|
cory Phone #: ###-####. Exterior shear nailing in areas 1,2,3,4 and 5 are now constructed as shown on approved modified structural plans. Did note that hold downs previously installed in area 4 are to small(STDH 10 and 8). Approved modified structural plans call for STDH 14 to be installed. Will need RFI from enginner of record showing installed straps are ok or an approved fix.
|
BLD-Framing/Rough-in | 9/28/2009 | 9/28/2009 | 9/28/2009 | P | FAIL |
Mike Jordan
|
|
|
Exterior shear nail inspection. Approved plans call for 16 gauge staples on SW1 walls only. Contractor has used staples on all shearwalls. Will need RFI from engineer noting ok to use staples on other shearwalls and spacing.
|
BLD-Framing/Rough-in | 9/25/2009 | 9/28/2009 | 9/28/2009 | A | NR |
Mike Jordan
|
|
|
cory Phone #: ###-####. rescheduled for pm.
|
BLD-Footing | 9/4/2009 | 9/4/2009 | 9/4/2009 | P | DONE |
Mike Jordan
|
|
|
interior footing and slab inspection//Corey Jacobsen ###-#### (ok to schedule insp. per DRS and 450). Structural plans still being reviewed for approval. Inspected interior footings and interior column pad footings for areas 1,2,3,4 and 5. Work done was in compliance with structural plans that were provided by Corey with CCI. It was made to very clear to Corey with CCI that if there are any discrepencies with in place work and final approved structural plans, that CCI is accepting all liability and will be required to make all repairs to bring structural portion into compliance. OK to do inspection per Bruce C. and Jason Blais.
|
BLD-Conference | 7/8/2009 | 7/8/2009 | 7/8/2009 | A | DONE |
Mike Jordan
|
|
|
Stopwork posted until no buikd agreement has been resolved.
|
BLD-Foundation | 7/1/2009 | 7/2/2009 | 7/2/2009 | P | PASS |
Mike Jordan
|
|
|
Cory Phone #: ###-####. Stemwalls for west wing.
|
BLD-Conference | 6/29/2009 | 7/1/2009 | 7/1/2009 | A | DONE |
Mike Jordan
|
|
|
meet at 9:00am on site please-Cory Phone #: ###-####
|
BLD-Footing | 6/29/2009 | 6/30/2009 | 6/30/2009 | A | PASS |
Mike Jordan
|
|
|
Corey Phone #: ###-####. Perimeter footings for west wing.
|
BLD-Foundation | 6/24/2009 | 6/24/2009 | 6/24/2009 | P | PASS |
Mike Jordan
|
|
|
randy Phone #: ###-####. Perimeter footings for main bldg as well as middle and west wings. Also delivered plan modifications to contractor.
|
BLD-Footing | 6/17/2009 | 6/18/2009 | 6/18/2009 | A | PART |
Mike Jordan
|
|
|
Randy Phone #: ###-####Perimeter footings for main enterance and bldg. Also for se, middle and a portion of the sw wings. No interior footings or column pad footings at this time. Also went over changes in fotting and reinforcement details to tie wings together.
|