Permit Information
Permit NumberBLD09-00464
StatusFinaled
Name CM COMPANY
Site Address 1010 W WASHINGTON ST
Project NameBOISE HIGH SCHOOL
Customer Number 
ePlanReviewNo
Description
(BOISE HIGH SCHOOL - WEST WING - SEISMIC UPGRADE) Perform select interior demolition at ceiling and floor at west wing perimeter per the reviewed plan to facilitate seismic strengthening in accordance with structural engineering evaluation using the 1994 UCBC Appendix Chapter 1 as the design guide for this historic structure. Work includes installation of epoxy and mechanical anchors, blocking and sheathing per the plans and engineering to secure the walls to floor and roof structure; portico / canopy components together and to structure; and interior drag struts and blocking; to add structural steel within stairs to provide added seismic support at the stair enclosure. Special inspection is required for epoxy & mechanical anchors per specified ICC Evaluation Services Reports, manufacture's installation instructions, structural engineers specifications; welding; high strength bolts; masonry infill of openings; removing of deteriorated mortar and repointing as designated on plans; to repair portions of ceilings and floor sheathing removed for upgrade and miscellaneous finishes per the reviewed plans. Any modifications of fire sprinkler or alarm systems require separate applications, plans and permits as regulated by fire department before work can be done. Electrical, plumbing & mechanical work requires separate trade permits attached to this building permit. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/11/20099/14/20099/14/2009APASS
DetailsTony Young
Please call Craig Stevens when available. Phone #: ###-#### Internet Inspection Request from: Erin Hoobing
DOC - Permit Finaled9/14/20099/14/20099/14/2009PPASS
DetailsTony Young
BLD-Final8/24/20098/25/20098/25/2009APASS
DetailsTony Young
Craig Phone #: ###-####
FIRE-Final Inspection8/20/20098/21/20098/21/2009PPASS
DetailsForrest France
Fire life safety passed per the scope of work.
BLD-Other8/14/20098/17/20098/18/2009PPART
DetailsDave Hannah
craig - steel Phone #: ###-#### parepit bracing of canopy
BLD-Framing/Rough-in7/24/20097/27/20097/27/2009APART
DetailsTony Young
craig Phone #: ###-####
steel angles in pront portico,, seismic braces,, ok pending S.I. reports
BLD-Framing/Rough-in7/7/20097/8/20097/8/2009APART
DetailsTony Young
Craig please call when you get to job site so he can meet you out back. Phone #: ###-####
seismic strapping in attic and other areas as noted on plans
BLD-Framing/Rough-in6/26/20096/29/20096/29/2009APART
DetailsTom Arcoraci
Craig Phone #: ###-#### wip ok
BLD-Framing/Rough-in6/17/20096/18/20096/18/2009PPART
DetailsJim Storey
Craig Phone #: ###-#### second floor class rms ok/ part of hall ok to sheet. drag beams not in place yet. si ok marked on plan as to location insp.