BLD-Final | 7/28/2009 | 7/28/2009 | 7/28/2009 | P | PASS |
Mike Jordan
|
|
|
kevin Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 7/27/2009 | 7/27/2009 | 7/27/2009 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection for remaining areas including A and C completed satisfactory.
|
BLD-Framing/Rough-in | 7/23/2009 | 7/24/2009 | 7/24/2009 | A | PASS |
Mike Jordan
|
|
|
kevin Phone #: ###-####. Ceiling grid at bookstore.
|
BLD-Final | 7/15/2009 | 7/16/2009 | 7/16/2009 | P | PART |
Tom Arcoraci
|
|
|
Kevin Phone #: ###-#### B and D area ok
|
FIRE-Final Inspection | 7/15/2009 | 7/16/2009 | 7/16/2009 | A | PART |
Troy Cobbley
|
|
|
Fire life safety in areas 'B' and 'D' is passed. These two areas okay to occupy per phase agreement.
|
FIRE-Final Inspection | 7/14/2009 | 7/14/2009 | 7/14/2009 | P | FAIL |
Troy Cobbley
|
|
|
Life safety in areas B and D is ok when the project related fire alarm for these areas is complete.
|
BLD-Final | 7/13/2009 | 7/14/2009 | 7/14/2009 | P | NR |
Tom Arcoraci
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 7/10/2009 | 7/13/2009 | 7/13/2009 | A | FAIL |
Troy Cobbley
|
|
|
The fire life safety is complete in Areas B and D and will be ok to occupy when the fire alarm system in these same two areas is complete.
|
BLD-Final | 7/10/2009 | 7/13/2009 | 7/13/2009 | P | NR |
Tom Arcoraci
|
|
|
kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 7/10/2009 | 7/13/2009 | 7/13/2009 | P | PASS |
Tom Arcoraci
|
|
|
kevin Phone #: ###-####
|
BLD-Final | 7/9/2009 | 7/10/2009 | 7/10/2009 | P | PART |
Jim Storey
|
|
|
kevin Phone #: ###-#### tactal signage at primary exit discharge. pending fires c/n
|
FIRE-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 | A | FAIL |
Troy Cobbley
|
|
|
All life safety items in areas B and D are ok except for three doors that require panic hardware and two emergency lights in the central garden area.
|
BLD-Other | 7/8/2009 | 7/8/2009 | 7/8/2009 | P | PART |
Mike Jordan
|
|
|
kevin Phone #: ###-####. Ceiling grid for area a.
|
BLD-Framing/Rough-in | 7/6/2009 | 7/7/2009 | 7/7/2009 | A | NR |
Mike Jordan
|
|
|
kevin - ceiling Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2009 | 7/2/2009 | 7/2/2009 | P | PART |
Mike Jordan
|
|
|
kevin Phone #: ###-####. Grid for area C only ok.
|
BLD-Framing/Rough-in | 6/23/2009 | 6/24/2009 | 6/24/2009 | A | PART |
Mike Jordan
|
|
|
kevin Phone #: ###-####. Ceiling grid at area D only.
|
BLD-Framing/Rough-in | 6/18/2009 | 6/19/2009 | 6/19/2009 | A | PART |
Mike Jordan
|
|
|
kevin Phone #: ###-####. Ceiling grid at area A only.
|
FIRE-Conference | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | DONE |
Troy Cobbley
|
|
|
I discussed exit sign placement with the general contractor
|
BLD-Framing/Rough-in | 5/26/2009 | 5/27/2009 | 5/27/2009 | A | PASS |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Verified backing for ada elements.
|
BLD-Framing/Rough-in | 5/22/2009 | 5/26/2009 | 5/26/2009 | A | PART |
Mike Jordan
|
|
|
kevin Phone #: ###-####. Framing for area A ok. Needs to verify backing for ada elements.
|
BLD-Framing/Rough-in | 5/13/2009 | 5/13/2009 | 5/13/2009 | P | PART |
Jim Sly
|
|
|
Kevin Phone #: ###-#### Framing OK all areas except area A.......pending Electr R/I approval.
|