BLD-Final | 9/28/2009 | 9/29/2009 | 9/29/2009 | A | PASS |
Dave Hannah
|
|
|
Ron Roberts-after 9:30 please Phone #: ###-####
|
DOC - Permit Finaled | 9/29/2009 | 9/29/2009 | 9/29/2009 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 8/27/2009 | 8/28/2009 | 8/28/2009 | A | NR |
Dave Hannah
|
|
|
Ron Phone #: ###-#### needs an elec final first
|
BLD-Energy code compliance | 7/16/2009 | 7/17/2009 | 7/17/2009 | A | PASS |
Dave Hannah
|
|
|
tad - please call 1/2 hr prior Phone #: ###-####
|
BLD-Framing/Rough-in | 7/16/2009 | 7/16/2009 | 7/17/2009 | P | PASS |
Dave Hannah
|
|
|
steve Phone #: ###-####
|
BLD-Framing/Rough-in | 6/17/2009 | 6/17/2009 | 6/18/2009 | P | NR |
Dave Hannah
|
|
|
Tad- still waiting on 2 interior walls for HVAC Phone #: ###-#### needs other trades to finish rough ins first
|
BLD-Conference | 6/15/2009 | 6/15/2009 | 6/16/2009 | P | PART |
Dave Hannah
|
|
|
Tad Phone #: ###-#### wall is about 3.5 ft from prop line window is ok but will need to fire rate new part of wall
|