BLD-Final | 5/11/2010 | 5/11/2010 | 5/11/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hour before Inspection requested from web by: James Larkin Phone #: ###-####
|
DOC - Permit Finaled | 5/11/2010 | 5/11/2010 | 5/11/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy issued.
|
BLD-Aging Inspection | 5/7/2010 | 5/7/2010 | 5/7/2010 | | PASS |
Mike Jordan
|
|
|
Work in progress. Should have final inspection within 1 week. Unit has been sold.
|
BLD-Energy code compliance | 3/1/2010 | 3/1/2010 | 3/1/2010 | P | NR |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 2/26/2010 | 2/26/2010 | 2/26/2010 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. ok to insul.
|
BLD-Wall cover | 2/4/2010 | 2/5/2010 | 2/5/2010 | A | NR |
Mike Jordan
|
|
|
House Wrap Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Wall cover | 2/2/2010 | 2/2/2010 | 2/2/2010 | A | PART |
Mike Jordan
|
|
|
House Wrap Phone #: ###-#### Internet Inspection Request from: James Larkin. Work in progress on installing the exterior weather resistive barrier.
|
BLD-Framing/Rough-in | 1/28/2010 | 1/28/2010 | 1/28/2010 | P | CANC |
Jim Sly
|
|
|
Jim this is for dire wall inspection Phone #: ###-#### Canc. by Contr.
|
BLD-Framing/Rough-in | 1/21/2010 | 1/21/2010 | 1/21/2010 | P | PASS |
Mike Jordan
|
|
|
Fire wall inspection please-Jim Phone #: ###-####. Face layer of 5/8 type x rock for 2hr. firewall. Also verified fire rated ply for laydown parapet.
|
BLD-Framing/Rough-in | 1/20/2010 | 1/20/2010 | 1/21/2010 | P | PART |
Mike Jordan
|
|
|
JIm-Fire wall construction inspection please Phone #: ###-####. BAse layer of 5/8 type x rock for 2hr. fire wall.
|
BLD-Framing/Rough-in | 1/8/2010 | 1/8/2010 | 1/8/2010 | P | PASS |
Mike Jordan
|
|
|
Fire wall construction inspection please-Jim Phone #: ###-####. Base and face layers of 5/8 type x rock at overbuild and 2nd. floor to underside of roof.. Also verified fire rated ply at laydown parapet.
|
BLD-Framing/Rough-in | 1/7/2010 | 1/7/2010 | 1/7/2010 | P | NR |
Mike Jordan
|
|
|
Firewall construction in ovrbuild Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Framing/Rough-in | 1/6/2010 | 1/6/2010 | 1/6/2010 | P | NR |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 1/5/2010 | 1/5/2010 | 1/5/2010 | P | PART |
Mike Jordan
|
|
|
Jim-Fire wall construction inspection please Phone #: ###-####. BAse layer of 5/8 type x rock for 2hr. firewall from 2nd floor ceiling to roofdeck.
|
BLD-Framing/Rough-in | 12/30/2009 | 12/30/2009 | 12/30/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 2nd floor, face layer of 5/8 type x rock, both sides for 2hr. firewall.
|
BLD-Framing/Rough-in | 12/23/2009 | 12/23/2009 | 12/23/2009 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin. 2nd floor, 1st. layer, both sides, 5/8 type x rock for 2hr. fire wall.
|
BLD-Framing/Rough-in | 12/23/2009 | 12/23/2009 | 12/23/2009 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Framing/Rough-in | 12/8/2009 | 12/8/2009 | 12/8/2009 | P | PART |
Mike Jordan
|
|
|
Fire Wall construction Phone #: ###-#### Internet Inspection Request from: James Larkin. Face layer of 5/8 type x rock, 1st. floor both sides for 2hr. firewall.
|
BLD-Framing/Rough-in | 12/6/2009 | 12/7/2009 | 12/7/2009 | P | PART |
Mike Jordan
|
|
|
Fire wall. Should be ready any time after 11:00 Phone #: ###-#### Internet Inspection Request from: James Larkin. 1st. floor, 1st. layer of 5/8 type x rock both sides for 2hr. firewall.
|
BLD-Framing/Rough-in | 12/4/2009 | 12/4/2009 | 12/4/2009 | P | NR |
Mike Jordan
|
|
|
Fire Wall Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Footing | 12/1/2009 | 12/1/2009 | 12/1/2009 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin. wip on interior footings, to be placed with slab on grade.
|
BLD-Energy code compliance | 11/24/2009 | 11/24/2009 | 11/24/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####Rigid foam insulation at interior side of stemwall.
|
BLD-Foundation | 11/20/2009 | 11/23/2009 | 11/23/2009 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 11/18/2009 | 11/19/2009 | 11/19/2009 | A | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 11/18/2009 | 11/18/2009 | 11/18/2009 | P | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####. reschduled for 11-19-09.
|