BLD-Final | 1/19/2010 | 1/20/2010 | 1/20/2010 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 1/20/2010 | 1/20/2010 | 1/20/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 1/19/2010 | 1/20/2010 | 1/20/2010 | A | FAIL |
Troy Cobbley
|
|
|
The duct smoke detector has been oriented incorrectly, has the wrong length of sample tube and does not shut down the hvac system when tested in heat mode.
|
FIRE-Final Inspection | 1/15/2010 | 1/15/2010 | 1/15/2010 | P | FAIL |
Troy Cobbley
|
|
|
This project was not ready for a final inspection so we performed a conference. A duct smoke detector will be required on RTU 4 along with the remote annunciator. Three doors need the correct single action hardware installed. Exit signs and emergency lights tested ok. The hood suppression system needs to be installed and tested as well as fire extinguishers installed.
|
BLD-Conference | 1/6/2010 | 1/6/2010 | 1/6/2010 | A | PASS |
Mike Jordan
|
|
|
Ceiling grid ok. wip on remainder of job. Almost ready for finals.
|
BLD-Other | 11/19/2009 | 11/19/2009 | 11/19/2009 | P | CANC |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 10/23/2009 | 10/26/2009 | 10/26/2009 | P | NR |
Mike Jordan
|
|
|
jason - ceiling grid Phone #: ###-####. Needs other trades ri insp. first.
|
BLD-Framing/Rough-in | 9/17/2009 | 9/18/2009 | 9/18/2009 | P | PASS |
Mike Jordan
|
|
|
jason Phone #: ###-####. All issues were resolved. ok to cover.
|
BLD-Framing/Rough-in | 9/11/2009 | 9/14/2009 | 9/14/2009 | A | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Needs to provide additional engineering for soffit to bottom of roof joist. Still needs plumbing ri insp. Mech contractor needs to pull mech permit. Also needs to add all backing in restrooms for ada equipment. Contractor will call back for anothrer framing insp.
|