BLD-Final | 8/31/2010 | 8/31/2010 | 8/31/2010 | P | DONE |
Jim Storey
|
|
|
archived si reports .
|
BLD-Final | 8/10/2010 | 8/11/2010 | 8/11/2010 | A | PASS |
Jim Storey
|
|
|
Kenny Phone #: ###-####
|
FIRE-Final Inspection | 8/4/2010 | 8/5/2010 | 8/5/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed. Correction items finished.
|
BLD-Framing/Rough-in | 7/6/2010 | 7/7/2010 | 7/7/2010 | A | PASS |
Jim Storey
|
|
|
ceiling grid inspection//Kenny Phone #: ###-####
|
BLD-Other | 7/6/2010 | 7/6/2010 | 7/6/2010 | P | PART |
Jim Storey
|
|
|
Kenny Phone #: ###-#### need hvac ceilling wire supports supply/return/vent fans.
|
FIRE-Conference | 7/1/2010 | 7/1/2010 | 7/1/2010 | P | DONE |
Forrest France
|
|
|
Discovered during and on site inspection request for fire sprinkler work that no fire alarm permit has been issued or applied for related to this building. Electrical contractor has installed a new fire alarm system including the panel, initiating and notification devices without a permit/ approved plans etc. Notified electrical contractor on site. General contractor was not available.
|
BLD-Framing/Rough-in | 6/17/2010 | 6/18/2010 | 6/18/2010 | P | PASS |
Jim Storey
|
|
|
Kenny Phone #: ###-####
|
BLD-Energy code compliance | 6/8/2010 | 6/8/2010 | 6/8/2010 | P | PASS |
Jim Storey
|
|
|
kenny Phone #: ###-####
|
BLD-Framing/Rough-in | 6/1/2010 | 6/2/2010 | 6/2/2010 | A | PASS |
Jim Storey
|
|
|
kenny Phone #: ###-####
|
BLD-Footing | 5/24/2010 | 5/24/2010 | 5/24/2010 | P | PASS |
Jim Storey
|
|
|
kenny Phone #: ###-#### slab rebar pour back ok
|
BLD-Footing | 4/28/2010 | 4/29/2010 | 4/29/2010 | P | PASS |
Jim Storey
|
|
|
kenny - rebar Phone #: ###-####
|
BLD-Other | 4/19/2010 | 4/20/2010 | 4/20/2010 | A | PASS |
Jim Storey
|
|
|
masonary inspection//Kenny Phone #: ###-####
|
BLD-Foundation | 4/12/2010 | 4/13/2010 | 4/13/2010 | A | PASS |
Jim Storey
|
|
|
Kenny Thompson Phone #: ###-#### loadding dock wall rebar ok.
|
FIRE-Conference | 4/7/2010 | 4/7/2010 | 4/7/2010 | P | DONE |
Forrest France
|
|
|
Regarding project related overhead fire sprinkler permit.
|
BLD-Footing | 4/6/2010 | 4/7/2010 | 4/7/2010 | P | PASS |
Jim Storey
|
|
|
kenny Phone #: ###-####
|
BLD-Framing/Rough-in | 3/23/2010 | 3/25/2010 | 3/26/2010 | P | PART |
Jim Storey
|
|
|
kenny - rebar Phone #: ###-#### rainned out. rebar ok
|
BLD-Framing/Rough-in | 3/23/2010 | 3/24/2010 | 3/24/2010 | P | PART |
Jim Storey
|
|
|
kenny - rebar Phone #: ###-#### ok si ok
|
BLD-Footing | 3/1/2010 | 3/2/2010 | 3/2/2010 | P | PASS |
Jim Storey
|
|
|
kenny Phone #: ###-####
|
BLD-Concrete | 2/25/2010 | 2/26/2010 | 2/26/2010 | P | PART |
Jim Storey
|
|
|
kenny- rebar Phone #: ###-#### pending si report.
|
BLD-Other | 2/24/2010 | 2/25/2010 | 2/25/2010 | P | PASS |
Jim Storey
|
|
|
kenny- rebar Phone #: ###-#### si on site south end panels ok
|
BLD-Footing | 12/2/2009 | 12/3/2009 | 12/3/2009 | P | PART |
Jim Storey
|
|
|
Kenny Phone #: ###-####ns and east ok pending si report.
|
FIRE-Conference | 11/24/2009 | 11/24/2009 | 11/27/2009 | P | DONE |
Forrest France
|
|
|
Regarding project related fire sprinkler permit work.
|
BLD-Concrete | 11/20/2009 | 11/23/2009 | 11/23/2009 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### interior ft in north slab and mat rebar ok to cover si reports pending.
|
BLD-Other | 11/19/2009 | 11/20/2009 | 11/20/2009 | P | PASS |
Jim Storey
|
|
|
Kenny Phone #: ###-####
|