BLD-Final | 12/21/2009 | 12/22/2009 | 12/22/2009 | A | PASS |
Mike Jordan
|
|
|
Mike,
Please call me when you are on your way. Troy has signed me off and you are all that is left. Thanks,
Todd Phone #: ###-#### Internet Inspection Request from: Todd Kurns. Ok for perm occ.
|
FIRE-Final Inspection | 12/17/2009 | 12/18/2009 | 12/18/2009 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Final | 11/24/2009 | 11/25/2009 | 11/25/2009 | A | PART |
Mike Jordan
|
|
|
Mike,
Can you give me a call when you are headed towards the job. I am not on site and need to meet you there to let you in.
Thanks,
Todd Phone #: ###-#### Internet Inspection Request from: Todd Kurns. Needs to resubmit plans to plan review showing correct layout and occ. type at training room or classroom. Noted total of 36 seats. Ok to give temp occ. per Bob Archibald.
|
FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is given with mark sentenos permission until the single action hardware is installed on the north exit door and the two overspaced sprinkler pendants.
|
FIRE-Final Inspection | 11/19/2009 | 11/19/2009 | 11/19/2009 | P | NR |
Forrest France
|
|
|
Project is not ready for inspection at this time per conversation with contractor, rescheduled as discussed.
|
BLD-Framing/Rough-in | 11/3/2009 | 11/4/2009 | 11/4/2009 | A | PART |
Mike Jordan
|
|
|
Todd Phone #: ###-####. pend. elec. inspection.
|