FIRE-Final Inspection | 12/10/2009 | 12/11/2009 | 12/11/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety site inspection passed, mag locks at stairway exit doors have been removed.
|
BLD-Final | 12/10/2009 | 12/11/2009 | 12/11/2009 | P | PASS |
Dave Hannah
|
|
|
Dan Phone #: ###-#### ok for perm occ
|
FIRE-Conference | 12/3/2009 | 12/3/2009 | 12/3/2009 | P | DONE |
Forrest France
|
|
|
Site visit with contractor regarding third floor exit signs, hardware at access control doors, upgrade agreement, first floor occupancy, and project schedule.
|
FIRE-Conference | 11/19/2009 | 11/19/2009 | 11/19/2009 | P | DONE |
Forrest France
|
|
|
On site visit regarding project details including fire alarm and sprinkler work, upgrade agreements, life safety issues, project schedule, requirements for certificate of occupancy, etc.
|
BLD-Framing/Rough-in | 11/18/2009 | 11/18/2009 | 11/18/2009 | P | PART |
Tony Young
|
|
|
Dan please call before going out Phone #: ###-#### int. walls on 3rd floor ok to cover,, need to verify braces later,, 8' o.c.
|