BLD-Final | 1/14/2010 | 1/14/2010 | 1/14/2010 | A | PASS |
Dave Hannah
|
|
|
All trades and fire final. P&Z says maybe today or tomorrow for insp- need to get this on TCO at least. please call. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman ok for perm occ after zoning finals
|
FIRE-Final Inspection | 1/13/2010 | 1/13/2010 | 1/14/2010 | A | PASS |
Forrest France
|
|
|
Corrections verified for compliance, fire life safety final approved.
|
BLD-Final | 1/13/2010 | 1/14/2010 | 1/14/2010 | P | CANC |
Dave Hannah
|
|
|
P&Z is pending- said sometime Thursday possible, Friday am for sure. need to at least get this on TCO as moving vans are scheduled for Friday AM. Fire, all other trades are final. Please call. Phone #: ###-#### Internet Inspection Request from: John Lodman Inspection cancelled from web by: John Lodman
|
FIRE-Final Inspection | 1/12/2010 | 1/12/2010 | 1/13/2010 | P | FAIL |
Forrest France
|
|
|
Missing exit signs per red-lines at four locations, post suite address, post two fire extinguishers at locations per discussion, project related fire sprinkler permit needs finaled.
|
BLD-Wall cover | 1/3/2010 | 1/4/2010 | 1/4/2010 | P | PART |
Dave Hannah
|
|
|
1 hour ceiling above alley entrance. rated access door added for electrical junction access. Phone #: ###-#### Internet Inspection Request from: John Lodman ok to cover
|
BLD-Framing/Rough-in | 12/14/2009 | 12/14/2009 | 12/14/2009 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### ok to cover after other trades get rough ins approved
|