DOC - Permit Finaled | | | 2/16/2011 | | DONE |
Tony Young
|
|
|
|
BLD-Final | 2/14/2011 | 2/14/2011 | 2/15/2011 | P | PASS |
Tony Young
|
|
|
Tony//scheduled by Ron Hill Phone #: ###-####
|
Extend Permit 90/180 days | | 12/22/2010 | 12/22/2010 | | DONE |
|
|
|
extend 90 days per Jason Blais
|
BLD-Aging Inspection | 9/22/2010 | 9/22/2010 | 9/24/2010 | | PEND |
Tony Young
|
|
|
|
BLD-Final | 6/21/2010 | 6/22/2010 | 6/22/2010 | A | PASS |
Tony Young
|
|
|
Dan Phone #: ###-####
|
FIRE-Final Inspection | 6/21/2010 | 6/21/2010 | 6/22/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety passed.
|
BLD-Aging Inspection | 6/15/2010 | 6/15/2010 | 6/15/2010 | | PEND |
Tony Young
|
|
|
|
FIRE-Conference | 4/12/2010 | 4/12/2010 | 4/12/2010 | P | DONE |
Forrest France
|
|
|
Conversation with contractor regarding NFPA 72 requirements for the manual pull station to be relocated due to the new exit path.
|
FIRE-Conference | 4/2/2010 | 4/5/2010 | 4/5/2010 | A | DONE |
Forrest France
|
|
|
On site meeting regarding new exit access a the 2nd floor north stairway including new doors, relocated exit signs, relocated MP station, gate to prevent travel below the level of exit discharge etc.
|
BLD-Framing/Rough-in | 1/26/2010 | 1/26/2010 | 1/26/2010 | P | CANC |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
FIRE-Final Inspection | 1/20/2010 | 1/22/2010 | 1/22/2010 | A | PART |
Forrest France
|
|
|
Fire life safety inspection passed for the 4th floor only at this time.
|
BLD-Final | 1/20/2010 | 1/22/2010 | 1/22/2010 | P | PART |
Tony Young
|
|
|
Dan Phone #: ###-####temp occ ok,, 4th floor,, may need to get mech permit by the end,, moving some ducts
|
FIRE-Final Inspection | 1/19/2010 | 1/19/2010 | 1/20/2010 | P | NR |
Forrest France
|
|
|
Pending project related fire alarm permit.
|
BLD-Conference | 1/12/2010 | 1/12/2010 | 1/15/2010 | P | DONE |
Forrest France
|
|
|
Regarding hardware at the inactive leaf on one pair of double doors.
|
BLD-Framing/Rough-in | 1/13/2010 | 1/14/2010 | 1/14/2010 | A | PASS |
Dave Hannah
|
|
|
Dan 2nd floor Phone #: ###-#### ok to rock around colmns
|
BLD-Conference | 1/11/2010 | 1/12/2010 | 1/12/2010 | A | PASS |
Dave Hannah
|
|
|
Dan Phone #: ###-####fire proofing details for columns ect
|
FIRE-Conference | 1/4/2010 | 1/4/2010 | 1/6/2010 | P | DONE |
Forrest France
|
|
|
Regarding completion of work at the 4th floor prior to the 2nd floor.
|
BLD-Framing/Rough-in | 12/3/2009 | 12/4/2009 | 12/4/2009 | A | PART |
Tony Young
|
|
|
Dan Phone #: ###-#### 4th floor walls ok pending elec pass
|