Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD10-00043
StatusFinaled
Name ST LUKES REG MED CNTR
Site Address 3000 S DENVER WAY
Project NameST LUKES LAUNDRY FACILITY
Customer Number 
ePlanReviewNo
Description
(ST. LUKE'S - CENTRAL LAUNDRY FACILITY) Additional Plan Modification - 10/12/10 - Due to mold mitigation and abatement, new windows and exterior wall finish & sheathing are being added to scope of work as approved under Modification of DRH09-00258. New exterior envelope components to comply with 2006 IECC. drs PLAN MODIFICATION 9/10/10 - SCOPE OF WORK REDUCED DUE TO FINANCIAL CONSTRAINTS. EXTERIOR MODIFICATIONS AND CANOPY ADDITIONS DELETED; INTERIOR FINISHES WITHIN ROOMS MARKED "FUTURE" TO REMAIN AS-IS; INTERIOR RESTROOM FINISHES & DIVIDERS TO REMAIN UNCHANGED; MISCELLANEOUS ARCH., MECH., ELECT., MINOR CHANGES OR SUBSTITUTIONS FOR COST SAVINGS. ALL ORIGINAL PLAN REVIEW COMMENTS OF ALL AGENCIES FOR ITEMS NOT REMOVED FROM SCOPE OF WORK ARE STILL APPLICABLE. ALL EXITING SYSTEM COMPONENTS (DOOR WIDTH, HARDWARE, CLEAR FLOOR SPACE, DOOR SWING, EXIT LIGHTING AND EMERGENCY LIGHTING, ETC. SHALL BE COMPLIANT WITH CURRENT CODE FOR LIFE SAFETY / EGRESS. DRS Remodel of existing 62,500 sq. ft. building for new laundry facility per approved plans. Demolition work done under separate permit, BLD09-02081. Work to include construction of non-combustible frame, drywall and finish of interior walls to create admin area, break, boiler, maintenance and lockers rooms; create receiving, dirty laundry, clean laundry, folding and shipping work areas; future offices on the first and second floor; stairs to a mechanical mezzanine and structural upgrades at existing roof structure for equipment and lateral support; reinforced concrete drainage trench & pit; and new footings, foundations, reinforced CMU and structural steel for new entry and entry covers. Work on electrical, mechanical, plumbing, sprinkler and alarms systems and accessibility compliance throughout the building. Special Inspections required as outlined on Sheet S-001 and attached "Project Start Up For Special Inspections" form. NOTE: This building is fully fire sprinklered for area increase. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/18/20115/18/20115/18/2011APASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble
FIRE-Conference5/10/20115/11/20115/11/2011ADONE
DetailsForrest France
On site conference with contractor regarding fire protection at the tape room and IFC 2006 and 2009 sec. 903.3.1.1, 903.3.1.1.1 (1)-(4/5) and 904.2.
BLD-Other3/28/20113/28/20113/28/2011APASS
DetailsJim Storey
archived PDF of si reports to case final ok
FIRE-Final Inspection2/24/20112/24/20112/24/2011APASS
DetailsForrest France
Phone #: ###-#### >> Inspection requested via web by phil doble
BLD-Final2/24/20112/24/20112/24/2011PPASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble life saftey ok for temp occ. pending public works and p$z
BLD-Conference2/22/20112/23/20112/23/2011APART
DetailsJim Storey
tour with planreviewer of project. exit door hardware/ exit ada signage/ bolt boiller to concrete.
BLD-Final2/22/20112/22/20112/23/2011PDEFR
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble
FIRE-Final Inspection2/22/20112/22/20112/23/2011APART
DetailsForrest France
C/N items include: provide min. 3' clear space at exisitng hydrants on the east and west sides of the building, missing EM lighting at the first floor lobby main entry, install one exit sign at the north laundry area, provide approved hardware at three exterior exit doors.
BLD-Final2/22/20112/22/20112/22/2011ADEFR
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble to pm
BLD-Framing/Rough-in1/13/20111/13/20111/13/2011APASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble ceilling ok to cover.
BLD-Aging Inspection11/15/201011/15/201011/15/2010 PASS
DetailsJim Storey
BLD-Framing/Rough-in9/13/20109/13/20109/13/2010PPASS
DetailsJim Storey
Phill ###-#### framing of interior wall
BLD-Wall cover8/26/20108/26/20108/26/2010APASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble center wall clean/dirty ok for cover one side pending trades
BLD-Wall cover8/13/20108/13/20108/16/2010PPASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by phil doble