BLD-Final | 8/19/2010 | 8/19/2010 | 8/19/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 8/19/2010 | 8/19/2010 | 8/19/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued.
|
BLD-Final | 8/17/2010 | 8/18/2010 | 8/18/2010 | P | NR |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Final | 8/17/2010 | 8/17/2010 | 8/17/2010 | P | NR |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin. NEeds electrical, plumbing and zoning finals.
|
BLD-Aging Inspection | 6/29/2010 | 6/29/2010 | 6/29/2010 | | PASS |
Mike Jordan
|
|
|
work is in progres.
|
BLD-Energy code compliance | 4/28/2010 | 4/28/2010 | 4/28/2010 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Framing/Rough-in | 4/28/2010 | 4/28/2010 | 4/28/2010 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. Lateral bracing completed.
|
BLD-Energy code compliance | 4/27/2010 | 4/27/2010 | 4/27/2010 | P | NR |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/27/2010 | 4/27/2010 | 4/27/2010 | A | NR |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/26/2010 | 4/26/2010 | 4/26/2010 | P | FAIL |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####. Complete lateral bracing. ok to insulate.
|
BLD-Framing/Rough-in | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | PASS |
Mike Jordan
|
|
|
Jim-Fire wall inspection please Phone #: ###-####. Verified fire rated plywood at laydown parapet at roof deck and also at overbuild areas.
|
BLD-Framing/Rough-in | 4/13/2010 | 4/13/2010 | 4/13/2010 | P | PASS |
Mike Jordan
|
|
|
BAse layer of 5/8 type x rock from ceiling to roof deck.
|
BLD-Framing/Rough-in | 4/7/2010 | 4/7/2010 | 4/7/2010 | P | NR |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/6/2010 | 4/6/2010 | 4/6/2010 | P | NR |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/6/2010 | 4/6/2010 | 4/6/2010 | A | NR |
Mike Jordan
|
|
|
firewall constuction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2010 | 4/5/2010 | 4/5/2010 | P | CANC |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 3/30/2010 | 3/30/2010 | 3/30/2010 | P | PASS |
Mike Jordan
|
|
|
Base and face layers of 5/8 typex rock for 2hr. firewall, remaining side, 2nd. floor.
|
BLD-Framing/Rough-in | 3/29/2010 | 3/30/2010 | 3/30/2010 | A | PASS |
Mike Jordan
|
|
|
Base and face layers of 5/8 type x rock for 2hr. firewall, 2nd. flloor, one side only.
|
BLD-Framing/Rough-in | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | NR |
Mike Jordan
|
|
|
firewall Inspection requested from web by: James Larkin Phone #: ###-####. Wiil reschedule for am inspection.
|
BLD-Framing/Rough-in | 3/25/2010 | 3/26/2010 | 3/26/2010 | P | NR |
Mike Jordan
|
|
|
Firewall consruction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 3/22/2010 | 3/22/2010 | 3/22/2010 | A | PART |
Jim Sly
|
|
|
Firewall construction Inspection requested from web by: James Larkin Phone #: ###-#### WIP.....Fire wall OK so far.
|
BLD-Framing/Rough-in | 3/19/2010 | 3/19/2010 | 3/19/2010 | P | PASS |
Mike Jordan
|
|
|
Jim Fire wall construction Phone #: ###-####.base and face layers of 2hr. firewall, 1st. floor.
|
BLD-Framing/Rough-in | 3/18/2010 | 3/18/2010 | 3/19/2010 | P | NR |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 3/17/2010 | 3/17/2010 | 3/17/2010 | A | PASS |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. Face layer, both sides of 5/8 type x rock for 2hr. firewall. 1st. floor completed. Inspected base layer on remaining side yesterday.
|
BLD-Framing/Rough-in | 3/16/2010 | 3/16/2010 | 3/17/2010 | P | PART |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. 5/8 type x rock, base layer, otherside.
|
BLD-Footing | 3/9/2010 | 3/10/2010 | 3/10/2010 | A | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####. Interior footings and column pad footings ok.
|
BLD-Energy code compliance | 3/8/2010 | 3/8/2010 | 3/8/2010 | P | PASS |
Mike Jordan
|
|
|
foundation information at garage wall Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Energy code compliance | 3/2/2010 | 3/3/2010 | 3/3/2010 | A | PASS |
Mike Jordan
|
|
|
insulation at foundation perimeter Inspection requested from web by: James Larkin Phone #: ###-####. Rigid foam insulation at interior side of stemwall.
|
BLD-Foundation | 2/26/2010 | 3/1/2010 | 3/1/2010 | P | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####
|
BLD-Footing | 2/25/2010 | 2/26/2010 | 2/26/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####. Perimeter footings only.
|