BLD-Final | 4/29/2010 | 4/30/2010 | 4/30/2010 | A | PASS |
Jim Storey
|
|
|
greg Phone #: ###-#### l/c isued
|
DOC - Permit Finaled | 4/30/2010 | 4/30/2010 | 4/30/2010 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 4/29/2010 | 4/30/2010 | 4/30/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety passed with the exception of two EM lights to be repaired, one exit sign to be added as discussed- will verify at structural final. Also noted timer installation at "push to exit" buttons for the first floor lobby is underway.
|
BLD-Framing/Rough-in | 4/27/2010 | 4/28/2010 | 4/28/2010 | A | PASS |
Dave Hannah
|
|
|
greg Phone #: ###-#### ok to cover wall on two added offices south end of floor
|
FIRE-Conference | 4/21/2010 | 4/21/2010 | 4/21/2010 | A | DONE |
Forrest France
|
|
|
Regarding fire extinguisher cabinets/locations and existing class II hose cabinets.
|
BLD-Conference | 4/8/2010 | 4/9/2010 | 4/9/2010 | A | PART |
Jim Storey
|
|
|
greg ###-#### ceilling ok ele pm insp./ arch unable to find mfg of old f/d working to get a listting.
|
BLD-Conference | 4/8/2010 | 4/8/2010 | 4/9/2010 | A | CANC |
Jim Storey
|
|
|
greg ###-####
|
BLD-Conference | 4/1/2010 | 4/1/2010 | 4/1/2010 | P | PART |
Jim Storey
|
|
|
need arch to supply damper listing.
|
BLD-Framing/Rough-in | 3/15/2010 | 3/16/2010 | 3/16/2010 | A | PART |
Jim Storey
|
|
|
3rd floor w/greg fpp permit. framing ok to cover pending ele approval/ cn above ceilling perimitor insulation must meet flame spread.
|
FIRE-Conference | 3/15/2010 | 3/15/2010 | 3/16/2010 | A | DONE |
Forrest France
|
|
|
Discussion with contractor regarding demo of existing hose cabinets, project related fire alarm work, and job schedule.
|
FIRE-Conference | 3/10/2010 | 3/10/2010 | 3/12/2010 | P | DONE |
Forrest France
|
|
|
Ref. IFC 2006 sec. 906.1 regarding existing class II hose stations at the third floor remodel area.
|