BLD-Aging Inspection | 2/14/2012 | 2/14/2012 | 2/14/2012 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 11/2/2011 | 11/3/2011 | 11/3/2011 | A | PASS |
Jim Storey
|
|
|
BO action on 9-22-2011
|
Extend Permit 90/180 days | | 9/22/2011 | 9/22/2011 | | DONE |
Jason Blais
|
|
|
|
BLD-Aging Inspection | 4/5/2011 | 4/5/2011 | 4/5/2011 | | PASS |
Jim Storey
|
|
|
Dan MacKinney on this project. He indicated that he is planning to complete the work under this permit, but he going to submit a plan mod. to include a cell tower and make fence and landscaping revisions required by P&Z. If you need to contact Dan about this permit, his number is ###-####.
|
BLD-Aging Inspection | 1/31/2011 | 1/31/2011 | 1/31/2011 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 11/29/2010 | 11/29/2010 | 12/2/2010 | | PASS |
Jim Storey
|
|
|
Dan MacKinney on this project. He indicated that he is planning to complete the work under this permit, but he going to submit a plan mod. to include a cell tower and make fence and landscaping revisions required by P&Z. If you need to contact Dan about this permit, his number is ###-####. 10/6/10 JCM
|
BLD-Aging Inspection | 9/21/2010 | 9/21/2010 | 9/27/2010 | | PASS |
Jim Storey
|
|
|
Talked to contractor, CUP paperwork was submitted to Boise City on 8/29.
|
BLD-Conference | 9/27/2010 | 9/27/2010 | 9/27/2010 | P | PASS |
Jim Storey
|
|
|
Talked to contractor, CUP paperwork was submitted to Boise City on 8/29.
|
BLD-Aging Inspection | 7/21/2010 | 7/21/2010 | 7/21/2010 | | PASS |
Jim Storey
|
|
|
no requist to insp.
|