Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD10-01001
StatusFinaled
Name BOISE CITY (BOISE PARKS & RECREATIO
Site Address 355 W JULIA DAVIS DR
Project NameZOO BOISE
Customer NumberPROJECT #688692
ePlanReviewNo
Description
Zoo Boise - Animal Health Complex - New Building - To construct a new 1,730 square foot, one story masonry and wood framed zoo animal health building with a 480 square foot exterior fenced holding area on the west side of the building. The building will include an exam area, a procedures room, x-ray and storage rooms and four separate interior animal holding areas. This permit also includes related site improvements. The required accessible restrooms are being provided in the adjacent modular office building. All construction per the approved plans and attached comment list. JCM 6-28-11 FINAL CERT OF VALUE PER GC $ 413,406.00 ///DLD
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/20/20115/20/20115/20/2011APASS
DetailsDave Hannah
dan - ###-#### ok for perm occ
BLD-Conference4/19/20114/19/20114/26/2011PPASS
DetailsDave Hannah
Steve Burns-temp occ expires 5-5-11 Phone #: ###-####
Extend Permit 90/180 days 4/26/20114/26/2011 DONE
DetailsTisha Gallop
Per approval from Jason Blais extend temporary occupancy 90 days for expiration date of 7/25/11; see attached documents.
BLD-Final2/1/20112/2/20112/2/2011PPART
DetailsDave Hannah
dan Phone #: ###-####ok for temp occ needs to finish installing cages and equipment
FIRE-Final Inspection2/1/20112/2/20112/2/2011APASS
DetailsForrest France
Door hardware approved per Building Official J. Blais. Ref. attatched documentation.
FIRE-Conference1/31/20112/1/20112/1/2011ADONE
DetailsForrest France
Regarding inspection notes, door hardware, project schedule, etc.
FIRE-Final Inspection1/25/20111/26/20111/26/2011AFAIL
DetailsTroy Cobbley
The inside and the outside enclosures have not been completed yet. Since they are included in the scope of work they will have to be finished or the scope of work modified. Also per a phone conversation with John Menard only the four rooms along the north wall, Holding, X ray, Storage, Holding, can have the round knobs for door hardware. All of the other doors are required to have single action hardware such as lever type. All other items appeared ok.
BLD-Aging Inspection1/11/20111/11/20111/11/2011 PASS
DetailsDave Hannah
work in progress
BLD-Foundation11/10/201011/10/201011/10/2010PPASS
DetailsDave Hannah
Dan Phone #: ###-####
BLD-Footing11/4/201011/5/201011/5/2010APASS
DetailsDave Hannah
Dan Phone #: ###-#### int ftgs ok to pour
BLD-Footing10/27/201010/27/201010/27/2010PPASS
DetailsDave Hannah
Dan Phone #: ###-####
BLD-Foundation10/27/201010/27/201010/27/2010PPASS
DetailsDave Hannah
BLD-Footing10/20/201010/20/201010/20/2010PPASS
DetailsDave Hannah
Dan Phone #: ###-####