BLD-Final | 8/26/2010 | 8/26/2010 | 8/26/2010 | P | PASS |
Tony Young
|
|
|
Dale Phone #: ###-####
|
FIRE-Final Inspection | 8/23/2010 | 8/24/2010 | 8/24/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety passed, corrections verified for completion.
|
BLD-Final | 8/23/2010 | 8/24/2010 | 8/24/2010 | P | NR |
Tony Young
|
|
|
Dale Phone #: ###-####,, need A D A requirments in rest rooms
|
FIRE-Final Inspection | 8/20/2010 | 8/20/2010 | 8/20/2010 | P | NR |
Forrest France
|
|
|
Project finishes underway.
|
FIRE-Conference | 8/18/2010 | 8/18/2010 | 8/18/2010 | A | DONE |
Forrest France
|
|
|
Fire sprinkler system modifications okayed to cover.
|
BLD-Other | 8/16/2010 | 8/17/2010 | 8/17/2010 | A | PASS |
Tony Young
|
|
|
dale Phone #: ###-####,, ceiling grid
|
BLD-Final | 8/16/2010 | 8/16/2010 | 8/17/2010 | P | NR |
Tony Young
|
|
|
dale Phone #: ###-####,, not ready for final,, needed a ceiling grid inspection
|
BLD-Framing/Rough-in | 8/6/2010 | 8/9/2010 | 8/9/2010 | A | PART |
Tony Young
|
|
|
dale Phone #: ###-####,, interior walls ok
|
BLD-Framing/Rough-in | 8/6/2010 | 8/6/2010 | 8/6/2010 | P | FAIL |
Tony Young
|
|
|
dale Phone #: ###-####,, need electrical rough in 1st for new walls,, need to provide demising wall studs at 16" o.c.,, brace walls at 45 degree,, not to cieling grids
|
BLD-Framing/Rough-in | 8/5/2010 | 8/6/2010 | 8/6/2010 | A | NR |
Tony Young
|
|
|
dale Phone #: ###-####,, need electrical 1st
|
BLD-Framing/Rough-in | 8/3/2010 | 8/3/2010 | 8/3/2010 | P | PART |
Dave Hannah
|
|
|
dale Phone #: ###-#### ok to cover rest rooms
|