BLD-Final | 8/2/2011 | 8/2/2011 | 8/3/2011 | P | PASS |
Dave Hannah
|
|
|
Rick ###-####
|
DOC - Permit Finaled | 8/3/2011 | 8/3/2011 | 8/3/2011 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 8/2/2011 | 8/2/2011 | 8/2/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/24/2011 | 3/24/2011 | 3/25/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 1/19/2011 | 1/19/2011 | 1/19/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Other | 11/16/2010 | 11/17/2010 | 11/17/2010 | A | PART |
Dave Hannah
|
|
|
rebar//Rick Phone #: ###-#### first 4ft lift on masonry wall M T I on site for rebar and grout testing
|
BLD-Foundation | 11/4/2010 | 11/5/2010 | 11/5/2010 | A | PART |
Dave Hannah
|
|
|
wants first am inspection if possible--rebar/slab inspection//Rick Phone #: ###-#### this was for rased seating ground level
|
BLD-Foundation | 10/5/2010 | 10/6/2010 | 10/6/2010 | P | PART |
Tony Young
|
|
|
rick pouring at 2 Phone #: ###-####,, looks ok,, MTI on site for special inspections
|
BLD-Foundation | 9/28/2010 | 9/30/2010 | 9/30/2010 | A | PART |
Dave Hannah
|
|
|
rick - rebar Phone #: ###-#### mti on site
|
BLD-Foundation | 9/28/2010 | 9/29/2010 | 9/29/2010 | A | PASS |
Dave Hannah
|
|
|
rick - rebar Phone #: ###-####
|
BLD-Footing | 9/15/2010 | 9/16/2010 | 9/16/2010 | A | PART |
Dave Hannah
|
|
|
Rick-pouring at 10 possible please-rebar inspection Phone #: ###-#### mti on site for spec inspec
|
BLD-Footing | 9/15/2010 | 9/15/2010 | 9/15/2010 | P | NR |
Dave Hannah
|
|
|
Rick-as late as possible please-rebar inspection Phone #: ###-####
|
BLD-Footing | 9/9/2010 | 9/10/2010 | 9/10/2010 | A | NR |
Dave Hannah
|
|
|
Rebar-after 10:00am Please-Rick Phone #: ###-#### crew working on ftgs MTI will be on site doing the spec inspection and testing concrete
|