BLD-Final | 4/4/2011 | 4/5/2011 | 4/5/2011 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 4/5/2011 | 4/5/2011 | 4/5/2011 | P | PASS |
Mike Jordan
|
|
|
Residential certificate of occupancy was issued.
|
BLD-Energy code compliance | 2/28/2011 | 3/1/2011 | 3/1/2011 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 3/1/2011 | 3/1/2011 | 3/1/2011 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####. All framing issues have been resolved.
|
BLD-Framing/Rough-in | 2/24/2011 | 2/25/2011 | 2/25/2011 | P | FAIL |
Mike Jordan
|
|
|
Brett ###-####. Provide tempered glazing at window in masterbath, add straps to portal frame.
|
BLD-Footing | 2/3/2011 | 2/4/2011 | 2/4/2011 | P | PART |
Mike Jordan
|
|
|
ryan Phone #: ###-####. work in progress. Set backs ok per plan.
|
BLD-Footing | 2/2/2011 | 2/3/2011 | 2/3/2011 | P | NR |
Mike Jordan
|
|
|
ryan Phone #: ###-####. Footings not yet excavated.
|