FIRE-Final Inspection | 11/19/2010 | 11/22/2010 | 11/22/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The Knox key box has been installed. All items pertaining to the high piled storage are to be addressed by the Boise City Fire Dept through a operational permit. This is per Scott Arellano and Mark Sentenno.
|
BLD-Final | 11/12/2010 | 11/16/2010 | 11/16/2010 | P | PASS |
Tom Arcoraci
|
|
|
ryan Phone #: ###-#### or ###-#### ok for perm occ when fire signs off
|
FIRE-Final Inspection | 11/12/2010 | 11/16/2010 | 11/16/2010 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Scotts permission until the Knox box that is on order has been installed.
|
BLD-Final | 11/2/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Tom Arcoraci
|
|
|
Ryan Phone #: ###-#### pending fire sign off
|
FIRE-Final Inspection | 11/2/2010 | 11/4/2010 | 11/4/2010 | P | FAIL |
Troy Cobbley
|
|
|
Provide emergency lighting for both the office and the warehouse areas. Provide additional exit door in warehouse. Provide verification on which doors are required to swing out. Remove all locking hatches and thumbturns. Provide automatic flush bolts on both main doors. Provide single action hardware on door from entrance office. Verify/provide at least a total of 13 (qty) "4A" classification fire extingguishers in the warehouse. Finish/final the project related fire alarm and fire sprinkler permits. Resubmit plans for review of high pile storage requirements of IFC chapter 23. Ryan Phone #: ###-####
|
FIRE-Final Inspection | 10/27/2010 | 10/29/2010 | 10/29/2010 | A | FAIL |
Forrest France
|
|
|
Items discussed include fire sprinkler system work underway, door hardware, emergency lights, code review notes, trade permits, etc. Building is not in condition for final fire life safety approval at this time.
|
BLD-Final | 10/27/2010 | 10/29/2010 | 10/29/2010 | P | CANC |
Tom Arcoraci
|
|
|
Ryan cell####-#### Phone #: ###-####//Tim Woodard wants you to also verify drain sink and related piping was removed from office/mezzanine area.//fire l/s failed so cancelled per Ryan Albers will call back to reschecule 10/29/10 11:02am//leg
|