BLD-Final | 6/14/2011 | 6/15/2011 | 6/15/2011 | A | PASS |
Dave Hannah
|
|
|
Steve Phone #: ###-#### ok for perm occ
|
FIRE-Final Inspection | 6/8/2011 | 6/8/2011 | 6/8/2011 | P | PASS |
Forrest France
|
|
|
C/N items finished with the exception of one EM light at the basement level to be repaired prior to structural final as discussed.
|
FIRE-Final Inspection | 4/8/2011 | 4/11/2011 | 4/11/2011 | A | FAIL |
Forrest France
|
|
|
Basement fire sprinkler system control valve at the DCVA #2 shutoff is closed. Noted two EM lights at the basement level are not functional. NOTE: Fire extinguisher certifications are now current.
|
BLD-Aging Inspection | 3/31/2011 | 3/31/2011 | 4/4/2011 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 1/27/2011 | 1/27/2011 | 1/27/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 11/23/2010 | 11/24/2010 | 11/25/2010 | P | FAIL |
Dave Hannah
|
|
|
Steve Phone #: ###-#### needs a fire life saftey final
|
FIRE-Final Inspection | 11/23/2010 | 11/24/2010 | 11/24/2010 | A | FAIL |
Forrest France
|
|
|
Existing portable fire extinguishers throughout both the first floor and basement are overdue annual certification. Provide a current inspection for the basement fire sprinkler system. Discussed schedule for occupancy.
|
BLD-Conference | 4/4/2011 | 4/4/2011 | | A | |
Dave Hannah
|
|
|
|