BLD-Final | 7/6/2012 | 7/6/2012 | 7/9/2012 | P | PASS |
Dave Hannah
|
|
|
Jeremy Phone #: ###-####
|
FIRE-Final Inspection | 7/6/2012 | 7/6/2012 | 7/6/2012 | P | PASS |
Forrest France
|
|
|
Final fire life safety inspection completed satisfactory. Contractor to repair one EM discharge light above the main entry/exit as discussed.
|
FIRE-Conference | 7/6/2012 | 7/6/2012 | 7/6/2012 | A | DONE |
Forrest France
|
|
|
Regarding life safety conditions for final occupancy approval.
|
FIRE-Conference | 6/18/2012 | 6/18/2012 | 6/18/2012 | P | DONE |
Troy Cobbley
|
|
|
Jeremy wanted a conference/walk through. I found one upright sprinkler head in a second floor room that is blocked by a surface mounted light. Also several pendant heads in the truck bay have ordinary temp heads in locations where intermediate and high temp. heads are required at the unit heaters. We also went over general life safety requirements.
|
BLD-Other | 4/5/2012 | 4/6/2012 | 4/6/2012 | A | PASS |
Dave Hannah
|
|
|
rebar//Jeremy Allen Phone #: ###-#### struc conc drive mat with mti on site conc sample was taken from end of pump today air at 5.3
|
BLD-Concrete | 4/2/2012 | 4/3/2012 | 4/3/2012 | A | PART |
Dave Hannah
|
|
|
Jeremy Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 3/26/2012 | 3/26/2012 | 3/30/2012 | P | PART |
Forrest France
|
|
|
Noted obstructed pendent heads at sheetrock ceilings.
|
BLD-Framing/Rough-in | 3/16/2012 | 3/16/2012 | 3/20/2012 | P | PART |
Dave Hannah
|
|
|
jeremy Phone #: ###-#### ceilings in truck bays ok to cover after lad support bracing is installed
|
BLD-Energy code compliance | 1/30/2012 | 1/30/2012 | 1/30/2012 | P | PASS |
Dave Hannah
|
|
|
jeremy Phone #: ###-####
|
BLD-Energy code compliance | 1/26/2012 | 1/26/2012 | 1/27/2012 | P | PART |
Dave Hannah
|
|
|
JEREMY Phone #: ###-#### ok to cover ext walls in living area
|
FIRE-Conference | 1/23/2012 | 1/23/2012 | 1/23/2012 | A | DONE |
Forrest France
|
|
|
Regarding project related FIR permits.
|
BLD-Framing/Rough-in | 1/17/2012 | 1/17/2012 | 1/17/2012 | P | PART |
Dave Hannah
|
|
|
jeremy Phone #: ###-#### ok to start insulating ext walls on living area
|
BLD-Framing/Rough-in | 12/16/2011 | 12/19/2011 | 12/19/2011 | P | PART |
Dave Hannah
|
|
|
jeremy - roof sheating nail inspection Phone #: ###-#### ok tro cover roof
|
BLD-Other | 12/15/2011 | 12/16/2011 | 12/16/2011 | A | NR |
Dave Hannah
|
|
|
jeremy - roof sheating nail inspection Phone #: ###-####
|
BLD-Energy code compliance | 12/6/2011 | 12/7/2011 | 12/7/2011 | A | PART |
Dave Hannah
|
|
|
jeremy Phone #: ###-#### elec room ok to cover
|
BLD-Framing/Rough-in | 11/30/2011 | 12/1/2011 | 12/2/2011 | A | PART |
Dave Hannah
|
|
|
jeremy - electrical room - 1 wall Phone #: ###-#### ok to insulate
|
BLD-Framing/Rough-in | 11/15/2011 | 11/16/2011 | 11/16/2011 | A | PASS |
Dave Hannah
|
|
|
jeremy - shear inspection Phone #: ###-#### ok to cover ext
|
BLD-Wall cover | 11/3/2011 | 11/4/2011 | 11/4/2011 | A | PART |
Dave Hannah
|
|
|
Exterior wall---Gene Phone #: ###-#### crew still working on sheeting and nailing
|
FIRE-Supply Line Flush | 10/25/2011 | 10/25/2011 | 10/26/2011 | P | PART |
Forrest France
|
|
|
|
BLD-Framing/Rough-in | 10/10/2011 | 10/10/2011 | 10/11/2011 | P | NR |
Dave Hannah
|
|
|
Gene Phone #: ###-####
|
BLD-Other | 9/1/2011 | 9/2/2011 | 9/2/2011 | P | PART |
Dave Hannah
|
|
|
bryce - rebar Phone #: ###-#### garage slab ok to place
|
BLD-Concrete | 9/1/2011 | 9/1/2011 | 9/1/2011 | A | PART |
Dave Hannah
|
|
|
Bryce Phone #: ###-####
|
BLD-Concrete | 8/31/2011 | 8/31/2011 | 9/1/2011 | P | PART |
Dave Hannah
|
|
|
Bryce Phone #: ###-#### north half ok to ppour slab
|
BLD-Foundation | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Dave Hannah
|
|
|
bryce Phone #: ###-####
|
BLD-Energy code compliance | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PART |
Dave Hannah
|
|
|
Bryce Phone #: ###-#### ridged insulation around stem wall garage bay slab on grade ok to backfill
|
BLD-Footing | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | PART |
Dave Hannah
|
|
|
bryce - rebar Phone #: ###-#### repair on section that was layed out wrong ok to pour
|
BLD-Foundation | 8/9/2011 | 8/10/2011 | 8/10/2011 | A | PART |
Dave Hannah
|
|
|
If possible before 9:00am please-Jeremy Allen Phone #: ###-#### south half garage area ok to place concrete MTI on to inspect and test
|
BLD-Footing | 8/4/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Jim Storey
|
|
|
bryce - rebar Phone #: ###-#### si to be on site ufer ground in place ok
|