Permit Information
Permit NumberBLD11-00101
StatusFinaled
Name ESI
Site Address 400 N MILWAUKEE ST
Project NameKOHL'S
Customer Number 
ePlanReviewNo
Description
KOHL'S DEPARTMENT STORE T.I.- Remodel of a two level, 83,730 sq. ft. (41,741 sq. ft. 1st level / 41,989 sq. ft. 2nd level) mercantile occupancy building, for continued same occupancy use by Kohl's. Kohl's will be an anchor store and is part of the unlimited area BTS Mall. The building is fully sprinklered. Work includes select interior demolition; modification and rebuild of all entry doors; non-combustible metal walls and drywall to create storage room areas, new His & Hers accessible restrooms, office and support areas, training and conference rooms; interior finishes, SAT, shelving, customer dressing rooms; new lighting fixturing, HVAC and plumbing; structural modifications at floor area at new escalator location and for new RTU’s. NOTE: modification to fire sprinkler and or the alarm system cannot be made until a separate permit is issued by the Fire Dept. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/1/20119/1/20119/1/2011PPASS
DetailsMike Jordan
alan Phone #: ###-####. ok for perm occ.
FIRE-Final Inspection8/30/20118/31/20118/31/2011APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection8/30/20118/30/20118/30/2011PFAIL
DetailsTroy Cobbley
All life safety items are passed except for two non-functioning emergency lights. One in the Southwest Stairwell and the other at the truck dock.
FIRE-Final Inspection8/24/20118/25/20118/25/2011ACANC
DetailsTroy Cobbley
This is a duplicate inspection that was set up for inspection performed 8/24/2011
FIRE-Final Inspection8/24/20118/24/20118/24/2011PCANC
DetailsTroy Cobbley
Todays inspection only covered the exit signs and emergency lights. See the electrical sheets of the city approved plans for the locations of exit signs and emergency lights that failed to operate.
BLD-Conference7/15/20117/15/20117/15/2011PCANC
DetailsMike Jordan
Office core grid for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. HArdlid at loading dock area.
BLD-Framing/Rough-in7/8/20117/8/20117/8/2011PPASS
DetailsMike Jordan
Framing inspection above escalator for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Steel stud framing for hardlid, 2nd. floor, above new escalators.
BLD-Framing/Rough-in6/30/20116/30/20116/30/2011PPART
DetailsMike Jordan
Framing inspection for jewelry hard lid to cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Pend. fire.
FIRE-Conference6/28/20116/29/20116/29/2011ADONE
DetailsForrest France
Regarding area of refuge notations per plan submital.
BLD-Framing/Rough-in6/23/20116/24/20116/24/2011APASS
DetailsMike Jordan
Ceiling inspection for cover at "E" line heading south for rest of second floor with the exception of the grid around the escalator. Phone #: ###-#### >> Inspection requested via web by alan fontenot
FIRE-Conference6/22/20116/23/20116/23/2011ADONE
DetailsForrest France
Alan phone #: ###-#### Regarding knox box location.
BLD-Conference6/20/20116/21/20116/21/2011APART
DetailsMike Jordan
Grid inspection at south and west perimeter walls second floor. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Remainder of clips have been installed, also ceiling grid ok for tile, 2nd flor, north of grid line e pending electrical and fire.
BLD-Other6/17/20116/17/20116/17/2011PPART
DetailsMike Jordan
Perimeter grid inspection for ceiling tile install. Phone #: ###-#### >> Inspection requested via web by alan fontenot. east adn north walls only, 2nd. floor at permiter only.( 6 bays from wall.) Contractor noted that he has gotten ok from other trades inspector to place perimeter tile.
BLD-Conference6/13/20116/13/20116/13/2011PPASS
DetailsMike Jordan
Framing inspection for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Interior steel stud framed walls and soffits for customer service areas at 1st. and 2nd. floors. Hardlids at north main enterance 1st. floor and south main enterance, 2nd. floor.
BLD-Framing/Rough-in6/2/20116/3/20116/3/2011APASS
DetailsMike Jordan
Framing Inspection First Floor. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Interior steel stud framed walls at 1st floor only, no grid.
BLD-Wall cover5/31/20115/31/20115/31/2011PPASS
DetailsMike Jordan
Inspect fire stop at perimeter walls for second floor slab.
Phone #: ###-#### >> Inspection requested via web by alan fontenot
BLD-Framing/Rough-in5/25/20115/26/20115/26/2011APART
DetailsMike Jordan
Need to inspect the fire caulking around MEP penetrations at the second floor slab to cover. Also need to inspect framing at sales floor.
Phone #: ###-#### >> Inspection requested via web by alan fontenot. Interior steel stud framed walls and furouts for 2nd. floor ok. Needs to complete the remainder of firecualking at penetrations.
BLD-Framing/Rough-in5/24/20115/25/20115/25/2011PPART
DetailsJim Storey
Walk with Troy Cobbley and inspect framing for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot ok to one side 2 nd floor east end and furout walls. need to fire stop floor penatrations and get plm ri/ hvac fire dampers aproved or left exposed.
BLD-Framing/Rough-in5/11/20115/12/20115/12/2011APART
DetailsMike Jordan
Alan, please call 30 mins prior, thanks. Phone #: ###-#### >> Inspection requested via web by alan fontenot. interior steel stud walls for 2nd floor restrooms only. 10ft. up. Still needs to add backing.