BLD-Final | 9/1/2011 | 9/1/2011 | 9/1/2011 | P | PASS |
Mike Jordan
|
|
|
alan Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 8/30/2011 | 8/31/2011 | 8/31/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 8/30/2011 | 8/30/2011 | 8/30/2011 | P | FAIL |
Troy Cobbley
|
|
|
All life safety items are passed except for two non-functioning emergency lights. One in the Southwest Stairwell and the other at the truck dock.
|
FIRE-Final Inspection | 8/24/2011 | 8/25/2011 | 8/25/2011 | A | CANC |
Troy Cobbley
|
|
|
This is a duplicate inspection that was set up for inspection performed 8/24/2011
|
FIRE-Final Inspection | 8/24/2011 | 8/24/2011 | 8/24/2011 | P | CANC |
Troy Cobbley
|
|
|
Todays inspection only covered the exit signs and emergency lights. See the electrical sheets of the city approved plans for the locations of exit signs and emergency lights that failed to operate.
|
BLD-Conference | 7/15/2011 | 7/15/2011 | 7/15/2011 | P | CANC |
Mike Jordan
|
|
|
Office core grid for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. HArdlid at loading dock area.
|
BLD-Framing/Rough-in | 7/8/2011 | 7/8/2011 | 7/8/2011 | P | PASS |
Mike Jordan
|
|
|
Framing inspection above escalator for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Steel stud framing for hardlid, 2nd. floor, above new escalators.
|
BLD-Framing/Rough-in | 6/30/2011 | 6/30/2011 | 6/30/2011 | P | PART |
Mike Jordan
|
|
|
Framing inspection for jewelry hard lid to cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Pend. fire.
|
FIRE-Conference | 6/28/2011 | 6/29/2011 | 6/29/2011 | A | DONE |
Forrest France
|
|
|
Regarding area of refuge notations per plan submital.
|
BLD-Framing/Rough-in | 6/23/2011 | 6/24/2011 | 6/24/2011 | A | PASS |
Mike Jordan
|
|
|
Ceiling inspection for cover at "E" line heading south for rest of second floor with the exception of the grid around the escalator. Phone #: ###-#### >> Inspection requested via web by alan fontenot
|
FIRE-Conference | 6/22/2011 | 6/23/2011 | 6/23/2011 | A | DONE |
Forrest France
|
|
|
Alan phone #: ###-#### Regarding knox box location.
|
BLD-Conference | 6/20/2011 | 6/21/2011 | 6/21/2011 | A | PART |
Mike Jordan
|
|
|
Grid inspection at south and west perimeter walls second floor. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Remainder of clips have been installed, also ceiling grid ok for tile, 2nd flor, north of grid line e pending electrical and fire.
|
BLD-Other | 6/17/2011 | 6/17/2011 | 6/17/2011 | P | PART |
Mike Jordan
|
|
|
Perimeter grid inspection for ceiling tile install. Phone #: ###-#### >> Inspection requested via web by alan fontenot. east adn north walls only, 2nd. floor at permiter only.( 6 bays from wall.) Contractor noted that he has gotten ok from other trades inspector to place perimeter tile.
|
BLD-Conference | 6/13/2011 | 6/13/2011 | 6/13/2011 | P | PASS |
Mike Jordan
|
|
|
Framing inspection for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Interior steel stud framed walls and soffits for customer service areas at 1st. and 2nd. floors. Hardlids at north main enterance 1st. floor and south main enterance, 2nd. floor.
|
BLD-Framing/Rough-in | 6/2/2011 | 6/3/2011 | 6/3/2011 | A | PASS |
Mike Jordan
|
|
|
Framing Inspection First Floor. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Interior steel stud framed walls at 1st floor only, no grid.
|
BLD-Wall cover | 5/31/2011 | 5/31/2011 | 5/31/2011 | P | PASS |
Mike Jordan
|
|
|
Inspect fire stop at perimeter walls for second floor slab. Phone #: ###-#### >> Inspection requested via web by alan fontenot
|
BLD-Framing/Rough-in | 5/25/2011 | 5/26/2011 | 5/26/2011 | A | PART |
Mike Jordan
|
|
|
Need to inspect the fire caulking around MEP penetrations at the second floor slab to cover. Also need to inspect framing at sales floor. Phone #: ###-#### >> Inspection requested via web by alan fontenot. Interior steel stud framed walls and furouts for 2nd. floor ok. Needs to complete the remainder of firecualking at penetrations.
|
BLD-Framing/Rough-in | 5/24/2011 | 5/25/2011 | 5/25/2011 | P | PART |
Jim Storey
|
|
|
Walk with Troy Cobbley and inspect framing for cover. Phone #: ###-#### >> Inspection requested via web by alan fontenot ok to one side 2 nd floor east end and furout walls. need to fire stop floor penatrations and get plm ri/ hvac fire dampers aproved or left exposed.
|
BLD-Framing/Rough-in | 5/11/2011 | 5/12/2011 | 5/12/2011 | A | PART |
Mike Jordan
|
|
|
Alan, please call 30 mins prior, thanks. Phone #: ###-#### >> Inspection requested via web by alan fontenot. interior steel stud walls for 2nd floor restrooms only. 10ft. up. Still needs to add backing.
|