BLD-Final | 9/23/2011 | 9/23/2011 | 9/23/2011 | P | PASS |
Mike Jordan
|
|
|
dennis Phone #: ###-####. All issues have been resolved! ok for perm occ!
|
BLD-Final | 9/21/2011 | 9/21/2011 | 9/21/2011 | P | PART |
Mike Jordan
|
|
|
Junior Phone #: ###-####. Ok for temp. occ. Needs to provide ada counter at POS, post occupant load map and finish installing clips at buffet grid system.
|
BLD-Final | 9/21/2011 | 9/21/2011 | 9/21/2011 | A | CANC |
Mike Jordan
|
|
|
Moved to pm.
|
BLD-Final | 9/20/2011 | 9/20/2011 | 9/21/2011 | P | NR |
Mike Jordan
|
|
|
Please call 30 min before thanks Phone #: ###-#### >> Inspection requested via web by Les Seal. Moved to am tommorrow.
|
FIRE-Final Inspection | 9/20/2011 | 9/20/2011 | 9/20/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 9/16/2011 | 9/19/2011 | 9/19/2011 | A | FAIL |
Troy Cobbley
|
|
|
Provide lever hardware on the office and kitchen restroom doors, remove the dead bolt from the office door, mount fire extinguishers and remove the palm fronds that are blocking the sidewall sprinkler heads in the seating area.
|
BLD-Conference | 9/7/2011 | 9/7/2011 | 9/7/2011 | P | CANC |
Mike Jordan
|
|
|
call when go out//John Lemley ###-####. Wrong permit was scheduled.
|
BLD-Other | 9/1/2011 | 9/2/2011 | 9/2/2011 | A | PART |
Mike Jordan
|
|
|
Ceiling Grid-- Jr Phone #: ###-#### or Dennis ###-####. Ok to place tile, will need to see packaging and safety film tags and clips.
|
BLD-Framing/Rough-in | 8/29/2011 | 8/29/2011 | 8/29/2011 | P | PART |
Mike Jordan
|
|
|
junior - grid inspection - please call 1/2 hr prior so he can meet you there Phone #: ###-####. Recieved paper work certification from Idaho window tinting for the installation of the sfaety laminate on glazing in hazerdous locations. Need to verify locations at end of booth seating.
|
FIRE-Conference | 8/24/2011 | 8/24/2011 | 8/24/2011 | P | DONE |
Troy Cobbley
|
|
|
JR and I discussed fire alarm remote annunciator requirements.
|
BLD-Framing/Rough-in | 7/14/2011 | 7/14/2011 | 7/14/2011 | A | FAIL |
Mike Jordan
|
|
|
Ceiling grid. Proposed glass tile for suspended grid system must be identified with manufactures mark, type and thickness, identification shall not be omitted unless an approved affidavit is furnished by glazing contractor as per IBC SEC. 2403.1. System must aslo be enginnered by a registered design professional for designs outside the scope of chapter 24 if the IBC per IBC SEC. 2404.4. Glass tile shall also meet IBC SEC. 2405 for sloped glazing and skylights. Also provide identification for glazing in pemanufactured panels for dining room per IBC SEC. 2403.1. Design must be submitted and approved by plan review staff prior to installation.
|
BLD-Other | 7/5/2011 | 7/5/2011 | 7/5/2011 | P | PART |
Mike Jordan
|
|
|
call 30 min prior to meet//grid inspection//Junior Phone #: ###-####. Ceiling grid in dining room and kitchen, except for center portion in soffit area.
|
BLD-Framing/Rough-in | 6/21/2011 | 6/22/2011 | 6/22/2011 | A | PART |
Tom Arcoraci
|
|
|
junior Phone #: ###-#### soffitt ok for cover
|
BLD-Conference | 6/15/2011 | 6/16/2011 | 6/16/2011 | A | CANC |
Mike Jordan
|
|
|
JR Phone #: ###-####
|
BLD-Framing/Rough-in | 6/13/2011 | 6/13/2011 | 6/13/2011 | P | PART |
Mike Jordan
|
|
|
Jr Phone #: ###-####. AMin dining area soffitt only. Also noted that tenant needs to provide a listed and aproved ceiling grid system that supports glass tile and submit for approval. Noted to tenant to not proceed with this portion of work until system has been approved.
|
BLD-Framing/Rough-in | 6/9/2011 | 6/9/2011 | 6/9/2011 | P | PASS |
Mike Jordan
|
|
|
Junior Phone #: ###-####. Hardlid framing in restrooms ok.
|
BLD-Framing/Rough-in | 6/8/2011 | 6/8/2011 | 6/8/2011 | P | FAIL |
Mike Jordan
|
|
|
Junior Phone #: ###-####. Needs to add vertical supports for hardlids at restrooms.
|
BLD-Framing/Rough-in | 5/19/2011 | 5/20/2011 | 5/20/2011 | A | PART |
Mike Jordan
|
|
|
Jr ###-#### Dennis Phone #: ###-####. Interior steel stud walls only. Needs to resubmit plan and detail showing new hardlid framing and calcs for addotional load put on roof trusses. Correction notice was issued.
|
BLD-Conference | 5/17/2011 | 5/18/2011 | 5/18/2011 | A | DONE |
Mike Jordan
|
|
|
Building conferance at 10:ooamMet on site with contractor, colliers rep. and tenant. Colliers to re-issue letter stating work to be done by tenant (Carpet and tile only) remainder of work is to be done by contractor.
|
BLD-Conference | 5/17/2011 | 5/17/2011 | 5/17/2011 | P | DONE |
Mike Jordan
|
|
|
Spoke to Jason Blais (building official) as well as christy with collier regarding letter that christy with colliers has written allowing the tenant to do parts of the tenant improvement work. After speaking to christy, it was noted that colliers does not want the tenant constructing soffits, hanging sheet rock or installing the grid ceiling. Will meet with colliers, general contractor and myself on jobsite tommorow at 10:00am to discuss with tenant what is to done by general contractor. Will have colliers reissue previous letter to clear up any confussion that the tenant may have and to precisley note work to be done by contractor.
|
BLD-Conference | 5/16/2011 | 5/16/2011 | 5/17/2011 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 5/12/2011 | 5/13/2011 | 5/13/2011 | A | DONE |
Mike Jordan
|
|
|
Dennis Phone #: ###-####. Spoke to dennis with HCD, resteraunt owner and electrical and plumbing inspectors onsite. It has been decided at this time to not allow one siding of interior partition walls with sheet rock due to majority of rough in work is not completed. Also spoke to contractor and owner about owner changing name on permit. Resteraunt owner has paid for the permit and has a letter from building owner, Colliers noting that this is ok and a list of work that is to be completed by resteraunt owner. A copy of letter has been given to building official and will discuss with him about additional work that resteraunt owner wants to complete.
|
BLD-Conference | 5/11/2011 | 5/11/2011 | 5/11/2011 | P | PASS |
Jim Storey
|
|
|
Owen,, frame ?s; Phone #: ###-#### ok to one side gyp on walls.
|
BLD-Conference | 4/28/2011 | 4/28/2011 | 4/28/2011 | P | DONE |
Mike Jordan
|
|
|
JR Phone #: ###-####. Went over shear wall notes and details with contractor.
|