(CITY BUFFET ASIAN RESTAURANT) Remodel combining two former spaces (approximately 2,700 sq. ft. and 5,400 sq. ft.) changing occupancy into a new 7,924 sq. ft. assembly restaurant space in existing shopping center per approved plans. Work to include select interior demolition of non-structural walls, finishes, electrical, mechanical, & plumbing with modifications to sprinkler and alarm system to be under separate permit as regulated by the fire department. There is an existing 1-hour fire rated wall creating the boundaries between tenants on north and south. Construct new walls to create the entrance / check-in area; kitchen / preparation area; storage, cooler , freezer units; accessible men's & women's restrooms and accessible route; and a private dining area. Interior finishes, electrical, mechanical, plumbing, sprinkler, alarm and Type I grease duct, hood & exhaust system and Type II hood & exhaust system with non-combustible support to structure above. NOTE: This existing building is fully fire sprinklered with 60 feet clearance all around for unlimited area (includes Shopko & strip mall areas). Occupancy use groups other than "B/M/F/S" cannot exceed 10% of existing building area under original UBC codes. The three "A2" occupancy max out the allowed 10% allowed for original buidling review process. drs 9/19/11 - Alternate letter & floor plan to establish actual occupant load for tenant space per exception to Sec. 1004.1.1, 2009 IBC, approved by Building Official, Jason Blais. Maximum occupant load for entire tenant space is 299 per letter and floor plan attached to this permit. A copy of the approved floor plan seating layout and occupant load's approved, shall be posted and maintained on the wall by front reception counter. The maximum occupant load of each seating area is to be posted. Area "A" (90), Area "B" (104) & Area "C" (40) and the total occupant load (299) at the main exit. An alarm notification system is not required. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/23/20119/23/20119/23/2011PPASS
DetailsMike Jordan
dennis Phone #: ###-####. All issues have been resolved! ok for perm occ!
BLD-Final9/21/20119/21/20119/21/2011PPART
DetailsMike Jordan
Junior Phone #: ###-####. Ok for temp. occ. Needs to provide ada counter at POS, post occupant load map and finish installing clips at buffet grid system.
BLD-Final9/21/20119/21/20119/21/2011ACANC
DetailsMike Jordan
Moved to pm.
BLD-Final9/20/20119/20/20119/21/2011PNR
DetailsMike Jordan
Please call 30 min before thanks Phone #: ###-#### >> Inspection requested via web by Les Seal. Moved to am tommorrow.
FIRE-Final Inspection9/20/20119/20/20119/20/2011APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection9/16/20119/19/20119/19/2011AFAIL
DetailsTroy Cobbley
Provide lever hardware on the office and kitchen restroom doors, remove the dead bolt from the office door, mount fire extinguishers and remove the palm fronds that are blocking the sidewall sprinkler heads in the seating area.
BLD-Conference9/7/20119/7/20119/7/2011PCANC
DetailsMike Jordan
call when go out//John Lemley ###-####. Wrong permit was scheduled.
BLD-Other9/1/20119/2/20119/2/2011APART
DetailsMike Jordan
Ceiling Grid-- Jr Phone #: ###-#### or Dennis ###-####. Ok to place tile, will need to see packaging and safety film tags and clips.
BLD-Framing/Rough-in8/29/20118/29/20118/29/2011PPART
DetailsMike Jordan
junior - grid inspection - please call 1/2 hr prior so he can meet you there Phone #: ###-####. Recieved paper work certification from Idaho window tinting for the installation of the sfaety laminate on glazing in hazerdous locations. Need to verify locations at end of booth seating.
FIRE-Conference8/24/20118/24/20118/24/2011PDONE
DetailsTroy Cobbley
JR and I discussed fire alarm remote annunciator requirements.
BLD-Framing/Rough-in7/14/20117/14/20117/14/2011AFAIL
DetailsMike Jordan
Ceiling grid. Proposed glass tile for suspended grid system must be identified with manufactures mark, type and thickness, identification shall not be omitted unless an approved affidavit is furnished by glazing contractor as per IBC SEC. 2403.1. System must aslo be enginnered by a registered design professional for designs outside the scope of chapter 24 if the IBC per IBC SEC. 2404.4. Glass tile shall also meet IBC SEC. 2405 for sloped glazing and skylights. Also provide identification for glazing in pemanufactured panels for dining room per IBC SEC. 2403.1. Design must be submitted and approved by plan review staff prior to installation.
BLD-Other7/5/20117/5/20117/5/2011PPART
DetailsMike Jordan
call 30 min prior to meet//grid inspection//Junior Phone #: ###-####. Ceiling grid in dining room and kitchen, except for center portion in soffit area.
BLD-Framing/Rough-in6/21/20116/22/20116/22/2011APART
DetailsTom Arcoraci
junior Phone #: ###-#### soffitt ok for cover
BLD-Conference6/15/20116/16/20116/16/2011ACANC
DetailsMike Jordan
JR Phone #: ###-####
BLD-Framing/Rough-in6/13/20116/13/20116/13/2011PPART
DetailsMike Jordan
Jr Phone #: ###-####. AMin dining area soffitt only. Also noted that tenant needs to provide a listed and aproved ceiling grid system that supports glass tile and submit for approval. Noted to tenant to not proceed with this portion of work until system has been approved.
BLD-Framing/Rough-in6/9/20116/9/20116/9/2011PPASS
DetailsMike Jordan
Junior Phone #: ###-####. Hardlid framing in restrooms ok.
BLD-Framing/Rough-in6/8/20116/8/20116/8/2011PFAIL
DetailsMike Jordan
Junior Phone #: ###-####. Needs to add vertical supports for hardlids at restrooms.
BLD-Framing/Rough-in5/19/20115/20/20115/20/2011APART
DetailsMike Jordan
Jr ###-#### Dennis Phone #: ###-####. Interior steel stud walls only. Needs to resubmit plan and detail showing new hardlid framing and calcs for addotional load put on roof trusses. Correction notice was issued.
BLD-Conference5/17/20115/18/20115/18/2011ADONE
DetailsMike Jordan
Building conferance at 10:ooamMet on site with contractor, colliers rep. and tenant. Colliers to re-issue letter stating work to be done by tenant (Carpet and tile only) remainder of work is to be done by contractor.
BLD-Conference5/17/20115/17/20115/17/2011PDONE
DetailsMike Jordan
Spoke to Jason Blais (building official) as well as christy with collier regarding letter that christy with colliers has written allowing the tenant to do parts of the tenant improvement work. After speaking to christy, it was noted that colliers does not want the tenant constructing soffits, hanging sheet rock or installing the grid ceiling. Will meet with colliers, general contractor and myself on jobsite tommorow at 10:00am to discuss with tenant what is to done by general contractor. Will have colliers reissue previous letter to clear up any confussion that the tenant may have and to precisley note work to be done by contractor.
BLD-Conference5/16/20115/16/20115/17/2011PCANC
DetailsMike Jordan
BLD-Conference5/12/20115/13/20115/13/2011ADONE
DetailsMike Jordan
Dennis Phone #: ###-####. Spoke to dennis with HCD, resteraunt owner and electrical and plumbing inspectors onsite. It has been decided at this time to not allow one siding of interior partition walls with sheet rock due to majority of rough in work is not completed. Also spoke to contractor and owner about owner changing name on permit. Resteraunt owner has paid for the permit and has a letter from building owner, Colliers noting that this is ok and a list of work that is to be completed by resteraunt owner. A copy of letter has been given to building official and will discuss with him about additional work that resteraunt owner wants to complete.
BLD-Conference5/11/20115/11/20115/11/2011PPASS
DetailsJim Storey
Owen,, frame ?s; Phone #: ###-#### ok to one side gyp on walls.
BLD-Conference4/28/20114/28/20114/28/2011PDONE
DetailsMike Jordan
JR Phone #: ###-####. Went over shear wall notes and details with contractor.