BLD-Conference | 9/28/2011 | 9/28/2011 | 9/28/2011 | P | DONE |
Tony Young
|
|
|
Joe needs c of o; Phone #: ###-####
|
BLD-Final | 9/28/2011 | 9/28/2011 | 9/28/2011 | A | PASS |
Tony Young
|
|
|
Conifmation received on soffit product approval and mechanical has been finaled. Certificate of Occupancy issued.
|
DOC - Permit Finaled | | | 9/28/2011 | | DONE |
|
|
|
|
BLD-Final | 9/21/2011 | 9/21/2011 | 9/21/2011 | P | PART |
Jim Storey
|
|
|
Phil Phone #: ###-#### bob a to verify hvac and documantation as to fire aprovals. temp completion isued/ rco pending.
|
BLD-Grading Inspection | 9/20/2011 | 9/20/2011 | 9/20/2011 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Conference | 7/12/2011 | 7/13/2011 | 7/13/2011 | A | PART |
Tony Young
|
|
|
check on soffit issue,, pending fire marshall approval of alternate
|
BLD-Conference | 6/22/2011 | 6/28/2011 | 6/30/2011 | A | PEND |
Tony Young
|
|
|
phil Phone #: ###-####,, follow up on soffit issue
|
BLD-Conference | 6/20/2011 | 6/22/2011 | 6/22/2011 | A | NR |
Tony Young
|
|
|
phil Phone #: ###-####,, follow up on soffit issue
|
BLD-Energy code compliance | 6/15/2011 | 6/20/2011 | 6/20/2011 | P | PART |
Tony Young
|
|
|
phil Phone #: ###-####,, still need approval on soffits from fire marshal on alternate method,, ok to cover inside
|
BLD-Framing/Rough-in | 6/15/2011 | 6/20/2011 | 6/20/2011 | A | PART |
Tony Young
|
|
|
phil Phone #: ###-####,,, frame ok,,, need to get fire marshals approval on alternate soffit
|
BLD-Framing/Rough-in | 6/14/2011 | 6/15/2011 | 6/15/2011 | A | PART |
Tony Young
|
|
|
phil Phone #: ###-####,, still need approval on soffit ratings... ok to insulate
|
BLD-Wall cover | 6/7/2011 | 6/7/2011 | 6/7/2011 | P | PART |
Tony Young
|
|
|
Phil Phone #: ###-####,, exterior shear ok now,, still need approval of soffit rating
|
BLD-Wall cover | 6/6/2011 | 6/7/2011 | 6/7/2011 | A | FAIL |
Tony Young
|
|
|
Phil Phone #: ###-####,, need to do shear nailing per plan,,, need to get plan review approval on soffit rating,, (painted cedar)
|
BLD-Foundation | 4/12/2011 | 4/13/2011 | 4/14/2011 | P | PART |
Tony Young
|
|
|
ian Phone #: ###-####
|
BLD-Foundation | 4/12/2011 | 4/12/2011 | 4/13/2011 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress
|
BLD-Footing | 4/11/2011 | 4/11/2011 | 4/12/2011 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress,, appears ok,, house corners surveyed in
|