Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD11-00825
StatusFinaled
Name BERMENSOLO CONSTRUCTION
Site Address 1511 N 9TH ST
Project NameLongfellow Elementary School
Customer Number 
ePlanReviewNo
Description
LONGFELLOW ELEMENTARY - RELOCATE PORTABLE CLASSROOM BUILDING- Portable Classroom #106 - Relocate a 912 sq. ft. portable school classroom, that was last permitted for original South Junior High, 805 Shoshone, under certificate of occupancy #04327and State of Idaho Tag #90558 A & B as a Type V-N Construction, "E1" occupancy use group, to new location at 1511 N 9th, Longfellow Elementary. Scope of work includes set up and anchoring per engineering & plans; to construct a new aluminum ramp, platform, stairs, handrails and edge protection systems providing shared accessibility access compliance for two relocatable classrooms. See BLD11-00824 for 2nd relocatable. There are no plumbing facilities in this unit. An existing accessible route from this relocated unit to the existing Multi-Purpose Building will provide access to existing restrooms facilities for students and staff. There are no changes to the existing building envelope beyond maintenance of siding & finish. Existing interior lighting fixtures to remain with changing of lamps and ballasts as allowed in 2009 IECC, Sec 101.4.3, Exc. #8. New battery pack exit sign and emergency lighting for interior room and at exterior landings being installed. Separate application, plans & permits for alarm system required as regulated by fire department. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/25/20117/26/20117/26/2011APASS
DetailsTony Young
tom Phone #: ###-####
FIRE-Final Inspection7/25/20117/25/20117/25/2011PPASS
DetailsForrest France
Fire life safety inspection completed satisfactory.
BLD-Final7/25/20117/25/20117/25/2011PPASS
DetailsTony Young
tom Phone #: ###-####
FIRE-Conference7/20/20117/20/20117/21/2011PDONE
DetailsForrest France
Regarding fire life safety inspection, items for final including PFE, emergency lighting, review notes, schedule, etc.
BLD-Conference6/28/20116/29/20116/29/2011APART
DetailsTony Young
Tom Phone #: ###-####,, ramp ?s
BLD-Framing/Rough-in6/22/20116/23/20116/23/2011APART
DetailsTony Young
Tom Phone #: ###-####,, skirting frame ok as built per architect,, will have interior walls also
BLD-Framing/Rough-in6/22/20116/22/20116/22/2011PFAIL
DetailsTony Young
Tom Phone #: ###-####,, not per plans,,, do per plans or get ok as built on skirting frame