BLD-Final | 3/20/2012 | 3/20/2012 | 3/20/2012 | P | PASS |
Mike Jordan
|
|
|
lester or denise Phone #: ###-####. Ok forperm occ.
|
BLD-Final | 3/19/2012 | 3/19/2012 | 3/19/2012 | P | NR |
Mike Jordan
|
|
|
Denise Phone #: ###-####. Wiil reschedule, Lacking paperwork from engineer.
|
FIRE-Final Inspection | 3/19/2012 | 3/19/2012 | 3/19/2012 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The opticon/gate was tested by Jeremy with the Boise Fire Dept.
|
BLD-Final | 1/13/2012 | 1/13/2012 | 1/13/2012 | P | PART |
Mike Jordan
|
|
|
Ray Kane Phone #: ###-####. ok for temp occ. Needs to provide code compliant guard and handrails at main stairway, note that their is an additional stairway and elevator for egress. Provide boots under sinks in restrooms 1st. floor, and provide code compliant passage hardware from accounting offices, dead has been removed. Also needs to have engineer of record approve non compliance issues noted on final special inspection letter.
|
FIRE-Final Inspection | 1/13/2012 | 1/13/2012 | 1/13/2012 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the new wrought iron gate with the opticon system has been installed and tested.
|
FIRE-Conference | 1/4/2012 | 1/4/2012 | 1/4/2012 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with the superintendant.
|
BLD-Other | 12/19/2011 | 12/20/2011 | 12/20/2011 | P | PART |
Mike Jordan
|
|
|
ray Phone #: ###-####. 1st. floor ceiling grid ok. Pending electrical and mech. inspections.
|
BLD-Framing/Rough-in | 12/7/2011 | 12/7/2011 | 12/7/2011 | P | PART |
Mike Jordan
|
|
|
ray - ceiling grid Phone #: ###-####. 2nd. floor grid ok pending other trades.
|
BLD-Framing/Rough-in | 11/29/2011 | 11/29/2011 | 11/29/2011 | P | PASS |
Mike Jordan
|
|
|
RAY Phone #: ###-####. 5/8 type x rock at elevator equipment room ok.
|
BLD-Other | 11/18/2011 | 11/21/2011 | 11/21/2011 | A | PASS |
Mike Jordan
|
|
|
ray - shear wall Phone #: ###-####. Shear walls interior side, 1st. floor.
|
BLD-Framing/Rough-in | 11/10/2011 | 11/14/2011 | 11/14/2011 | A | PASS |
Mike Jordan
|
|
|
ray Phone #: ###-####. 1st. floor interior stel stud framed walls for main front office and restrooms, aslo demissing walls for glass adn door assembly areas in warehouse.
|
BLD-Framing/Rough-in | 11/3/2011 | 11/3/2011 | 11/3/2011 | P | PASS |
Mike Jordan
|
|
|
2nd floor office area//Ray Kane Phone #: ###-####. Interior steel stud framed walls for 2nd. floor ok.
|
BLD-Conference | 10/28/2011 | 10/28/2011 | 10/28/2011 | P | PART |
Mike Jordan
|
|
|
Interior steel stud framing, 2nd. floor, work in progress. Ok to one side after electrical rough in.
|
BLD-Other | 10/19/2011 | 10/21/2011 | 10/21/2011 | A | PASS |
Jim Storey
|
|
|
shear wall--Ray Phone #: ###-#### exterior sheer walls #1 ok to cover exterior
|
BLD-Framing/Rough-in | 10/13/2011 | 10/14/2011 | 10/14/2011 | A | PASS |
Jim Storey
|
|
|
Bearing wall prior to cover---Ray Phone #: ###-####
|
BLD-Foundation | 8/29/2011 | 8/31/2011 | 8/31/2011 | A | PART |
Mike Jordan
|
|
|
ray Phone #: ###-####. Stemwall for office area. Needs to adjust #4 ties at columns. Special inspector on site, will inspect repair.
|
BLD-Footing | 8/25/2011 | 8/26/2011 | 8/26/2011 | A | PASS |
Mike Jordan
|
|
|
Ray Phone #: ###-####. Perimeter footings for office area ok. Special inspection
|
BLD-Footing | 8/18/2011 | 8/22/2011 | 8/22/2011 | A | PASS |
Mike Jordan
|
|
|
ray Phone #: ###-####. Perimeter footings on gridlines 1 nd 6 and grids A and E, loading dock footins as well as elevator pit section.
|