Permit Information
Permit NumberBLD11-01267
StatusFinaled
Name INLAND IDAHO LLC
Site Address 13626 W BALDCYPRESS ST
Project NameAFFINITY - SECTION A
Customer Number 
ePlanReviewNo
Description
AFFINITY AT BOISE- Section A- Section 'A' (West Wing) to construct a four story 1-hour fire rated, wood frame, 32-unit, commercial apartment building of 25,296 sq. ft.(6412 s.f. - 1st fl / 6,497 s.f. - 2 thru 4th fl.). There are 12 units @742 s.f.; 4 @ 751 s.f.; 4 @ 553 s.f. and 12 @ 568 s.f.. A 2-hour combination fire wall & Horizontal exit is being constructed between the West Wing and Center Core portion for allowable area compliance. This building is fully sprinkler W/ 13R system for allowable area increase, addition of 1-story and for occupancy use compliance; alarm with notification system; 1-hour exit corridors connecting the 2-hour stair enclosure and horizontal exit; and mechanical shaft assemblies are indicated as 2-hour rated. Each floor has one exit into a rated stair enclosure and 1 exit through a horizontal exit. All work to be in accordance with the reviewed plans, red-lined notres on plans and attached plan review comments & conditions of all provided plan reviews. CUP10-00052 DRH10-00222 12/14/11 - New Sheets A2.5.1, A2.5.2, A2.5.3, A4.3, A4.5, A8.0, A8.1, A10.0 & A10.1 SUBMITTED 11/18/11 INSERTED INTO OFFICE COPY OF PLANS AND COPY OF SHEETS TO JOB SITE FOR INSTALL IN FIELD COPY.
Sheets S2.3.3, S2.5.2, S2.5.3 & S5.1 SUBMITTED 11/18/11 INSERTED INTO OFFICE COPY OF PLANS AND COPY TO FIELD FOR JOB SET.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/24/20128/24/20128/24/2012PPASS
DetailsJim Sly
Ed Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection8/20/20128/21/20128/21/2012APASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final7/3/20127/5/20127/5/2012PPART
DetailsJim Sly
rob this is for the 3rd & 4th floors Phone #: ###-####
OK for Temp Occ 3rd and 4th floors...tower 1 and 2 (A&B) Pending fire approval....See Bldg Permit # BLD11-01268 and Fir11-00662.
FIRE-Final Inspection7/2/20127/2/20127/2/2012AFAIL
DetailsTroy Cobbley
Area "A" 3rd and 4th floors life safety will be a pass when the project related fire alarm system for this area is tested. Smoke alarms tested.
BLD-Other6/25/20126/25/20126/25/2012PPASS
DetailsJim Sly
Temporary Certificate of Occupancy Phone #: ###-#### >> Inspection requested via web by Rob Fraser
OK for Temp Occ. See prev. fire notes.
BLD-Final6/13/20126/14/20126/14/2012PNR
DetailsJim Sly
Rob Phone #: ###-####
FIRE-Final Inspection6/13/20126/14/20126/14/2012APART
DetailsTroy Cobbley
Life safety passed in area "A" and "B", first and second floors. A temporary occupancy is given with Romeo and Scott's permission.
FIRE-Final Inspection6/13/20126/13/20126/13/2012PFAIL
DetailsTroy Cobbley
Todays inspection was for area "A" and "B", first and second floors. Many emergency lights are not functioning or have not been installed. Several exit signs are not working. Fire extinguisher placement appears ok. Fire hydrant barrel orientation has been modified as requested. Per the revised building and fire review notes and verified by phone conversation with scott arellano the Area of Refuge communication system is not required but since a system has been installed it must function. Per scott the system does not need to call out but must atleast contact a central location. Currently the head end equipment is located at the fire alarm system remote annunciator in the main lobby. Scott was ok with this location.
FIRE-Alarm Testing6/12/20126/12/20126/12/2012PDONE
DetailsTroy Cobbley
For todays inspection I finished testing the residence room smoke alarms in the first floor north section up to the fire wall.
FIRE-Alarm Testing6/11/20126/11/20126/12/2012PDONE
DetailsTroy Cobbley
Todays inspection I walked through areas A and B, all of the second floor and the west half of the first floor. I tested the residential smoke alarms in these areas.
BLD-Conference6/6/20126/7/20126/7/2012ADONE
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Met with Rob to go over requirements for Phased Finals.
FIRE-Conference5/21/20125/21/20125/21/2012PDONE
DetailsTroy Cobbley
Rod and I went over life safety requirements. I went over the three options for fire dept access designation. The fire hydrant in the northwest corner of the property needs the 5" outlet turned to where it is accessible to the fire dept. A knox box needs to be provided. It appears that exit sign/emergency lights, if placed per plans, will be adequate. The "area of refuge" is noted in the fire dept review as being placed in the stairwells with the requirements for communication. Per Rod the "area of refuge" is in the main corridor. I deferred that any changes will need to be requested through Scott Arellano in plan review. I suggested that the architect become involved.
FIRE-Conference4/27/20124/27/20124/27/2012PDONE
DetailsTroy Cobbley
The standpipe hose valves located on all of the floors at the fire wall per the sprinkler plans were to be mounted recessed in the corridor walls. They have been installed surface mounted on the walls and are possibly encroaching into the egress path. After speaking to Dan Stuart, I spoke to the job site superintendant about having the architect submit to the plan reviewer for approval of this installation.
BLD-Framing/Rough-in3/13/20123/13/20123/13/2012PNR
DetailsJim Sly
rob - 2nd and 3rd floor corridors Phone #: ###-####
Need to complete Sheetrock on ceiling.
BLD-Conference2/24/20122/29/20122/29/2012ADONE
DetailsJim Sly
10:00 AM Meeting - Phased turnover conference with Romeo Jervaise and Inland. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Framing/Rough-in2/22/20122/23/20122/23/2012APASS
DetailsJim Sly
Trash Rooms on 1st, 2nd, 3rd, 4th floors. Room #157, 257, 357, 457. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Conference2/20/20122/21/20122/21/2012APASS
DetailsJim Sly
2-HR Fire Wall above ceiling in Unit 408. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Other2/16/20122/16/20122/16/2012PFAIL
DetailsJim Sly
2-hr wall inspection at trusses above 4th floor ceiling. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Not complete.
BLD-Wall cover2/9/20122/9/20122/9/2012PPART
DetailsJim Sly
Trash chute sheetrock shaft installation inspection. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Energy code compliance2/6/20122/7/20122/7/2012PPASS
DetailsJim Sly
Energy and fire-caulk inspection for Units 107 - 112 on Tower 1. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Energy code compliance2/4/20122/6/20122/6/2012ACANC
DetailsJim Sly
BLD-Energy code compliance2/3/20122/6/20122/6/2012APART
DetailsJim Sly
Energy code and fire-caulking re-inspection for units 102 thru 112. Phone #: ###-#### >> Inspection requested via web by Rob Fraser (102 thru 108 OK)
BLD-Energy code compliance2/2/20122/3/20122/4/2012PCANC
DetailsJim Sly
Tower 1 - 1st floor energy compliance and fire-caulking inspection (units 101 - 112). Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Energy code compliance2/1/20122/2/20122/2/2012APASS
DetailsJim Sly
Energy compliance (insulation) and fire-caulking inspection for Tower 1 2nd floor - units 201 thru 212. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Conference2/1/20122/1/20122/1/2012PCANC
DetailsJim Sly
Rob phone
BLD-Other1/31/20122/1/20122/1/2012APART
DetailsJim Sly
Rob phone 3rd floor fire collars
BLD-Energy code compliance1/31/20121/31/20121/31/2012PNR
DetailsJim Sly
3rd floor energy inspection/fire collars. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Other1/30/20121/31/20121/31/2012APART
DetailsJim Sly
2-hr wall construction in the attic for cover. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
2hr wall NR....8 units 3rd floor South end Tower 1....OK to cover.
BLD-Conference1/27/20121/27/20121/27/2012PPART
DetailsJim Sly
3rd floor rough-in cover inspection. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
2 units ...South end tower 1.....OK
BLD-Framing/Rough-in1/25/20121/26/20121/26/2012APASS
DetailsJim Sly
Stair Tower #1 and #2 Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Energy code compliance1/25/20121/26/20121/26/2012APASS
DetailsJim Sly
Energy compliance for units 407 - 410. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Energy code compliance1/24/20121/25/20121/25/2012APART
DetailsJim Sly
Units 401thru 406........OK
BLD-Energy code compliance1/20/20121/24/20121/24/2012ANR
DetailsJim Sly
Units 401 through 406 Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Framing/Rough-in1/23/20121/24/20121/24/2012APASS
DetailsJim Sly
rob Phone #: ###-####
Units 401-406
BLD-Framing/Rough-in1/20/20121/23/20121/23/2012ANR
DetailsJim Sly
Cover inspection for units 401 through 406 Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Firestopping not complete.
BLD-Conference1/18/20121/19/20121/19/2012APART
DetailsJim Sly
Elevator shaft #1 framing inspection. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Framing OK
BLD-Framing/Rough-in1/13/20121/17/20121/17/2012ANR
DetailsJim Sly
4th floor rough-in framing inspection. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Conference1/11/20121/12/20121/12/2012APART
DetailsJim Sly
rob Phone #: 901-054
Floor to floor straps on exterior wall ....North 1/2 of tower 1.....OK.
BLD-Conference1/10/20121/10/20121/10/2012PDONE
DetailsJim Sly
ROB Phone #: ###-####
Walk thru ....tower 1
BLD-Other12/19/201112/20/201112/21/2011APASS
DetailsJim Sly
Roof nailing for dry-in northwest corner of Tower #1. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
BLD-Conference12/15/201112/16/201112/16/2011ADONE
DetailsJim Sly
Rob Phone #: ###-####
Brought in approx 8 approved re-submittal plan sheets and went over changes with Ben......framing supervisor. Met with Electr and fire sprinkler Contr. to review firestopping.
BLD-Other12/7/201112/12/201112/12/2011APART
DetailsJim Sly
Roof nailing inspection for North end of Tower #1. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Nailing OK
BLD-Framing/Rough-in12/5/201112/5/201112/5/2011PCANC
DetailsJim Sly
ed Phone #: ###-####
Roof nailing......frost on roof....no inspection.
BLD-Other12/1/201112/2/201112/2/2011PNR
DetailsJim Sly
Roof nailing inspection. Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Not ready.
BLD-Other11/28/201112/1/201112/1/2011APART
DetailsJim Sly
Exterior shear nailing for Tower 1 Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Exterior shear nailing for East side of West wing......OK
BLD-Wall cover11/28/201111/28/201111/28/2011PPART
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Rob Fraser
Exterior West wall (West wing) shear nailing OK.
BLD-Other11/17/201111/17/201111/17/2011PPART
DetailsJim Sly
shear nail insp//Rob ###-####
2nd floor Center Core West OK
BLD-Other11/9/201111/9/201111/9/2011PPART
DetailsJim Sly
shear wall nailing//Ed Cuttlers Phone #: ###-####
OKd two shear walls 2nd floor center wing West. OKd shear nailing....West wing South stairway....North stairway wall. Met with Tracy......Electr contractor to discuss fire stopping.
BLD-Conference11/8/201111/8/201111/8/2011PDONE
DetailsJim Sly
rob Phone #: 901-054
Pre-Constr. Conference.....Plumbers. Met with Plumbers to discuss firestopping issues.
BLD-Other10/31/201111/1/201111/1/2011APASS
DetailsTom Arcoraci
Sheer wall--Rob Phone #: ###-#### 2 hr wall shear riser room shear ok
BLD-Framing/Rough-in10/27/201110/27/201110/28/2011PPART
DetailsJim Sly
Ed Cuttlers Phone #: ###-####
Shear...West wing gridH1-4to5. OK
BLD-Other9/20/20119/21/20119/21/2011APART
DetailsJim Sly
rebar insp for the elevator pit//Rob Phone #: ###-####
MTI on site.
BLD-Footing9/20/20119/20/20119/20/2011PPART
DetailsJim Sly
rob - around 3 if possible please Phone #: ###-####
Footings West wing OK pending MTI approvals.
BLD-Footing9/16/20119/19/20119/19/2011PPART
DetailsJim Sly
Rob Phone #: ###-####
Select footings.....West wing.....OK pending MTI special inspections, tests and approvals.