BLD-Final | 3/15/2012 | 3/15/2012 | 3/15/2012 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ. Special inspection reports were reviewed from shell and core and found to be ok.
|
BLD-Final | 3/14/2012 | 3/15/2012 | 3/15/2012 | A | PASS |
Mike Jordan
|
|
|
Stu Phone #: ###-####. ok for temp occ. Waiting on special inspection welding report on shell permit.
|
FIRE-Final Inspection | 3/13/2012 | 3/14/2012 | 3/14/2012 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 3/12/2012 | 3/13/2012 | 3/13/2012 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the Demo/shell permit has been inspected/finaled. I will be meeting Joe with J and B Construction in the morning.
|
FIRE-Final Inspection | 3/5/2012 | 3/6/2012 | 3/6/2012 | P | FAIL |
Troy Cobbley
|
|
|
Provide the annual inspection for the fire extinguishers, provide the wire shelving for the racks or move the racks apart, provide the minumum 4" high address numbers, provide/repair the exit discharge lights and provide the delayed egress hardware for testing.
|
FIRE-Final Inspection | 3/2/2012 | 3/2/2012 | 3/2/2012 | P | NR |
Forrest France
|
|
|
Missing two exit signs, post building address, delayed egress hardware is not yet installed. Discussed general fire life safety requirements.
|
BLD-Other | 2/28/2012 | 2/28/2012 | 2/28/2012 | P | PASS |
Mike Jordan
|
|
|
stewart - ceiling grid inspection Phone #: ###-####
|
BLD-Framing/Rough-in | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | FAIL |
Mike Jordan
|
|
|
ceiling grid inspection please-Stu Phone #: ###-####
|
BLD-Other | 2/24/2012 | 2/24/2012 | 2/24/2012 | P | CANC |
Dave Hannah
|
|
|
hector - ceiling grid - late as possible please Phone #: ###-####
per Stuart Lee called to cancel inspection as the electrical did not pass.
|
BLD-Framing/Rough-in | 1/5/2012 | 1/6/2012 | 1/6/2012 | P | PASS |
Mike Jordan
|
|
|
late pm//Hector Paez Phone #: ###-####. Interior steel stud walls, soffits and hardlids only. No grid. Also will need special inspection on welding at new vestibule.
|