Permit Information
Permit NumberBLD11-01395
StatusFinaled
Name ROBERT GOEBEL GENERAL CONTRACTOR IN
Site Address 534 N MILWAUKEE ST
Project NameBOISE TOWNE PLAZA
Customer Number 
ePlanReviewYes
Description
(NORDSTROM RACK) Interior remodel of an existing 36,432 square foot retail tenant space in an existing 37,500 square foot building. The West wall is shared with Shape Up Outlets.The East wal is shared with Old Navy. Work to include: construct new interior non-structural wall partitions to create a new entry vestibule, men's & women's dressing rooms, tailor room, locker room, break room, mother's room, personnel offices, maintenance room, stock & storage rooms, men's & women's accessible restrooms, and merchandise sales areas; new casework for retail sales floor; install a new dual height (hi-lo) accessible drinking fountain; install a service sink; new suspended ceiling grid system installed per CISCA guidelines; related interior finishes in compliance with chapter 8 of the 2009 IBC; installation of new lighting; plumbing, mechanical, and electrical work. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. NOTE: "This building is fully Fire Sprinklered for building area increase and also has an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department." A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/15/20123/15/20123/15/2012PPASS
DetailsMike Jordan
Ok for perm occ. Special inspection reports were reviewed from shell and core and found to be ok.
BLD-Final3/14/20123/15/20123/15/2012APASS
DetailsMike Jordan
Stu Phone #: ###-####. ok for temp occ. Waiting on special inspection welding report on shell permit.
FIRE-Final Inspection3/13/20123/14/20123/14/2012APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection3/12/20123/13/20123/13/2012PFAIL
DetailsTroy Cobbley
Life safety will be ok to final when the Demo/shell permit has been inspected/finaled. I will be meeting Joe with J and B Construction in the morning.
FIRE-Final Inspection3/5/20123/6/20123/6/2012PFAIL
DetailsTroy Cobbley
Provide the annual inspection for the fire extinguishers, provide the wire shelving for the racks or move the racks apart, provide the minumum 4" high address numbers, provide/repair the exit discharge lights and provide the delayed egress hardware for testing.
FIRE-Final Inspection3/2/20123/2/20123/2/2012PNR
DetailsForrest France
Missing two exit signs, post building address, delayed egress hardware is not yet installed. Discussed general fire life safety requirements.
BLD-Other2/28/20122/28/20122/28/2012PPASS
DetailsMike Jordan
stewart - ceiling grid inspection Phone #: ###-####
BLD-Framing/Rough-in2/27/20122/28/20122/28/2012AFAIL
DetailsMike Jordan
ceiling grid inspection please-Stu Phone #: ###-####
BLD-Other2/24/20122/24/20122/24/2012PCANC
DetailsDave Hannah
hector - ceiling grid - late as possible please Phone #: ###-####
per Stuart Lee called to cancel inspection as the electrical did not pass.
BLD-Framing/Rough-in1/5/20121/6/20121/6/2012PPASS
DetailsMike Jordan
late pm//Hector Paez Phone #: ###-####. Interior steel stud walls, soffits and hardlids only. No grid. Also will need special inspection on welding at new vestibule.