BLD-Final | 8/5/2011 | 8/8/2011 | 8/8/2011 | A | PASS |
Jim Storey
|
|
|
|
BLD-Final | 7/22/2011 | 7/22/2011 | 7/22/2011 | A | PART |
Jim Storey
|
|
|
ok for temp occ/ need to reinsp. south wall after infil.
|
FIRE-Final Inspection | 7/7/2011 | 7/8/2011 | 7/8/2011 | A | PASS |
Forrest France
|
|
|
Field verified correction items are finished, life safety is acceptable pending vent infill and paper faced insulation is concealed- to be done prior to structural final as discussed.
|
FIRE-Final Inspection | 6/30/2011 | 7/6/2011 | 7/7/2011 | A | PART |
Forrest France
|
|
|
Final pending correction items.
|
BLD-Conference | 7/7/2011 | 7/7/2011 | 7/7/2011 | P | PART |
Jim Storey
|
|
|
reviewed how to infil vent holes on fire wall south side of tennet.
|
BLD-Final | 6/30/2011 | 7/1/2011 | 7/1/2011 | P | PART |
Jim Storey
|
|
|
Madison or Meredith-Please call at least 30 mins prior to inspection Phone #: ###-#### conf. need vents filled per boise city agreement with prevous tenent .
|
FIRE-Final Inspection | 6/30/2011 | 6/30/2011 | 6/30/2011 | P | FAIL |
Forrest France
|
|
|
Noted items include; post premise identification as discussed, provide "door to remain unlocked.." signage at the main entry/exit, fire extinguishers must be posted on brackets/ hangers, exposed paper faced insulation must be concealed, ramp at the island per attatched drawing is not built.
|