BLD-Final | 11/9/2011 | 11/9/2011 | 11/9/2011 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 11/9/2011 | 11/9/2011 | 11/9/2011 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 11/8/2011 | 11/9/2011 | 11/9/2011 | A | NR |
Mike Jordan
|
|
|
Gary Phone #: ###-####. Rescheduled for pm inspection. Needs to prepair door hardware issues.
|
FIRE-Final Inspection | 11/8/2011 | 11/9/2011 | 11/9/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 10/27/2011 | 10/28/2011 | 10/28/2011 | A | FAIL |
Troy Cobbley
|
|
|
The door hardware for doors 109A and 109B does not match the approved plans, door schedules, on sheet A4. A fire watch was also required but has not been approved by the fire marshal. The project related fire sprinkler permit is finaled but the project related fire alarm permit has not been reviewed, issued, installed or inspected. A final building inspection has not been scheduled by the contractor.
|
BLD-Framing/Rough-in | 10/13/2011 | 10/14/2011 | 10/14/2011 | P | PASS |
Tom Arcoraci
|
|
|
glen - early afternoon please Phone #: ###-####
|
FIRE-Conference | 10/14/2011 | 10/14/2011 | 10/14/2011 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the general contractor about potential fire alarm issues due to new wall/room layout. He stated that CheckPoint would be the contractor and they work directly through PetsMart.
|
BLD-Framing/Rough-in | 9/29/2011 | 9/30/2011 | 9/30/2011 | P | PASS |
Mike Jordan
|
|
|
early pm//Glen Phone #: ###-####
|
BLD-Framing/Rough-in | 9/28/2011 | 9/29/2011 | 9/29/2011 | A | NR |
Mike Jordan
|
|
|
Glen Phone #: ###-####. Needs rough in inspection first.
|
BLD-Framing/Rough-in | 9/7/2011 | 9/8/2011 | 9/8/2011 | A | PART |
Mike Jordan
|
|
|
Glen Phone #: ###-####. INterior steel stud wall demissing wall for stockroom and new adaption area only.
|