FIRE-Final Inspection | 6/28/2012 | 6/29/2012 | 6/29/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. C/N items finished.
|
BLD-Final | 6/28/2012 | 6/29/2012 | 6/29/2012 | P | PASS |
Jim Storey
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil
|
DOC - Permit Finaled | 6/29/2012 | 6/29/2012 | 6/29/2012 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Alarm Testing | 6/27/2012 | 6/27/2012 | 6/28/2012 | A | PART |
Forrest France
|
|
|
See project related FIR.
|
FIRE-Final Inspection | 6/28/2012 | 6/28/2012 | 6/28/2012 | P | PART |
Forrest France
|
|
|
Final pending address numbers, missing tile at the computer room, signage at the door to the FACP, exit discharge light at the Myrtle street side, points map at the FACP.
|
FIRE-Final Inspection | 6/25/2012 | 6/28/2012 | 6/28/2012 | A | CANC |
Forrest France
|
|
|
As early as possible Phone #: 6314646 >> Inspection requested via mobile web by Gil
|
BLD-Other | 6/14/2012 | 6/14/2012 | 6/15/2012 | P | CANC |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil ceiling grid last room ok to cover
|
FIRE-Sprinkler Rough-in | 5/25/2012 | 5/25/2012 | 5/25/2012 | A | PART |
Forrest France
|
|
|
Reference dated and initialed annotations on FP plans for current locations approved for cover.
|
BLD-Wall cover | 5/23/2012 | 5/23/2012 | 5/23/2012 | P | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil ok to cover wall xray room and ceiling in other rooms after elec r/i
|
BLD-Wall cover | 5/3/2012 | 5/3/2012 | 5/3/2012 | A | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil the walls in the ultsound room ok to cover and the ceiling in the lounge ok to cover
|
BLD-Other | 4/13/2012 | 4/16/2012 | 4/16/2012 | A | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil ceiling grid in the braek room and dressing rooms ok to cover.
|
BLD-Framing/Rough-in | 3/29/2012 | 3/29/2012 | 3/29/2012 | A | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil ok to cover secvon phase
|
BLD-Other | 3/20/2012 | 3/21/2012 | 3/21/2012 | A | PART |
Dave Hannah
|
|
|
As early as possible Phone #: 6318646 >> Inspection requested via mobile web by Gil the ceiling grid in exray rooms ok to cover after elec oks
|
BLD-Framing/Rough-in | 3/15/2012 | 3/15/2012 | 3/15/2012 | A | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil ok to cover wall in x ray rooms
|
BLD-Final | 2/28/2012 | 2/29/2012 | 2/29/2012 | A | PART |
Dave Hannah
|
|
|
for temp//Gil Phone #: ###-#### ok to occ phase 1
|
FIRE-Conference | 2/28/2012 | 2/28/2012 | 2/28/2012 | P | DONE |
Forrest France
|
|
|
Regarding phasing.
|
FIRE-Final Inspection | 2/28/2012 | 2/28/2012 | 2/28/2012 | A | PART |
Forrest France
|
|
|
Partial completion- new reception, waiting, consultation, blood draw and nurse station only. Noted one exit sign to be repaired, one a/v to be adjusted.
|
BLD-Other | 2/14/2012 | 2/14/2012 | 2/15/2012 | A | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 2086318646 >> Inspection requested via mobile web by Gil ceiling grid in first phase ok to cover
|
BLD-Framing/Rough-in | 1/10/2012 | 1/11/2012 | 1/11/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: 6318646 >> Inspection requested via mobile web by Gil falash&ross
|
BLD-Other | 12/6/2011 | 12/7/2011 | 12/7/2011 | A | PART |
Dave Hannah
|
|
|
Please call prior to arrival//Ceiling grid---Gil Phone #: ###-#### ok after elec mri room
|
BLD-Framing/Rough-in | 11/17/2011 | 11/18/2011 | 11/18/2011 | A | PART |
Dave Hannah
|
|
|
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by gil/falashandross ok to cover walls in mri area
|
BLD-Footing | 11/11/2011 | 11/14/2011 | 11/14/2011 | A | PASS |
Dave Hannah
|
|
|
As early as possible Phone #: 6318646 >> Inspection requested via mobile web by gil/falashandross int column ftgs ok to place concrete
|
BLD-Footing | 10/21/2011 | 10/21/2011 | 10/24/2011 | P | PASS |
Dave Hannah
|
|
|
scott - pouring at 1 pm Phone #: ###-####
|
BLD-Framing/Rough-in | 10/20/2011 | 10/20/2011 | 10/20/2011 | P | PART |
Dave Hannah
|
|
|
Gill Phone #: ###-#### walls for the elec static room ok to one side
|