BLD-Final | 2/20/2012 | 2/21/2012 | 2/21/2012 | P | PASS |
Jim Sly
|
|
|
Call Darren 1/2 prior Phone #: ###-#### >> Inspection requested via web by Jeff Giddings OK for Perm Occ.
|
FIRE-Final Inspection | 2/20/2012 | 2/21/2012 | 2/21/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 2/16/2012 | 2/16/2012 | 2/16/2012 | P | CANC |
Troy Cobbley
|
|
|
Project was not ready for a final inspection yet. Darren and I went over all life safety items. Everything is good for a final life safety sign off when the project related fire alarm permit for the door magnets has been inspected and approved. Also an as-built is needed for the other fire alarm permit due to the duct smoke detectors being shown in the wrong area.
|
BLD-Other | 1/30/2012 | 1/31/2012 | 1/31/2012 | A | PASS |
Jim Sly
|
|
|
ceiling grid -- Darren Phone #: ###-####
|
FIRE-Conference | 1/24/2012 | 1/24/2012 | 1/24/2012 | P | DONE |
Troy Cobbley
|
|
|
Darren and I spoke about the two doors that will not arrive prior to the building being occupied. I was ok with verifying their install and hardware when a building final was requested at the same time the duct smoke detectors were addressed.
|
BLD-Framing/Rough-in | 1/20/2012 | 1/23/2012 | 1/23/2012 | A | PASS |
Jim Sly
|
|
|
darrin Phone #: ###-####
|
FIRE-Conference | 1/20/2012 | 1/23/2012 | 1/23/2012 | A | DONE |
Troy Cobbley
|
|
|
This conference was a request for a temporary occupancy due to the duct smoke detectors for two unit not being installed yet. I deferred the request to Romeo Gervais.
|