BLD-Final | 3/6/2014 | 3/6/2014 | 3/6/2014 | A | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 3/6/2014 | 3/6/2014 | 3/6/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 1/31/2014 | 2/3/2014 | 2/3/2014 | A | PEND |
Dave Hannah
|
|
|
Meet with ESI and CTA Architects, ESI field office, Please contact Adam in advance to ensure CTA can meet at the same time. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 11/20/2013 | 11/20/2013 | 11/21/2013 | P | PART |
Dave Hannah
|
|
|
1ST FL CEILING - jeff Phone #: ###-#### hard lid lobby area ok to cover
|
BLD-Framing/Rough-in | 11/12/2013 | 11/13/2013 | 11/13/2013 | A | PART |
Dave Hannah
|
|
|
Rescheduled from 11/12/13, Shell and Core Exterior fireproofing inspection, prior to cover on 9th, 10th and 14th Floor , exterior perimeter. Jamal is requesting a walk at 10:30 am. Thanks. oAdam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to insulate and cover perm walls and columns
|
BLD-Framing/Rough-in | 11/6/2013 | 11/12/2013 | 11/12/2013 | A | CANC |
Tom Arcoraci
|
|
|
Shell and core exterior fireproofing inspection, prior to cover, on 9th, 10th and 14th floors, exterior perimeter. Jamal is requesting a walk at 10:30 am. Thanks. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 10/22/2013 | 10/24/2013 | 10/24/2013 | A | DONE |
Dave Hannah
|
|
|
Dave, Need to get Troy out for an inspection on Grease Duct in Alley, MECH is not under my control to schedule inspection. Would like to see if we could coordinate a on site conference with Troy in the morning, 10/23/13 Please call me when possible. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/24/2013 | 10/24/2013 | 10/24/2013 | A | PART |
Dave Hannah
|
|
|
Inspection scheduled via John Woods. Adam is off site this morning, contact John for inspection needs. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked floors 1-17 with john
|
BLD-Framing/Rough-in | 10/22/2013 | 10/23/2013 | 10/23/2013 | A | PART |
Dave Hannah
|
|
|
Framing inspection for John Woods, also while on site, confirm framing sign offs to ESI binder for 12th and 9th floor TI''s. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson slab edge fire proofing ok 16 -10 at tower crain location also ok to cover 15&16 at same loction
|
BLD-Wall cover | 10/16/2013 | 10/17/2013 | 10/17/2013 | A | FAIL |
Dave Hannah
|
|
|
Request for cover inspection on 8th street grease duct at 805 Building in alley. Coordinate inspection with Roger ###-####. Thanks Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Wall cover | 10/3/2013 | 10/3/2013 | 10/4/2013 | P | PART |
Dave Hannah
|
|
|
8th floor shell and core perimeter fire proofing verification. Exterior wall. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson ext walls and columns ok to insulate and cover
|
BLD-Conference | 9/30/2013 | 10/1/2013 | 10/2/2013 | A | PEND |
Dave Hannah
|
|
|
Weekly Shell and Core inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 9/23/2013 | 9/24/2013 | 9/24/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Core and Shell inspection walk.
Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 9/16/2013 | 9/17/2013 | 9/19/2013 | A | PART |
Dave Hannah
|
|
|
Shell and Core Weekly Inspection. Stair Framing at 16 to 17th as well.
Thanks, Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly inspection walk of Shell and Core. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 9/3/2013 | 9/5/2013 | 9/5/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly inspection request. Shell and Core.
Thanks, Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 8/26/2013 | 8/27/2013 | 8/28/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Shell and Core inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 8/12/2013 | 8/13/2013 | 8/15/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly inspection walk, Adam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 8/5/2013 | 8/6/2013 | 8/7/2013 | A | DONE |
Dave Hannah
|
|
|
Please note weekly inspection for shell and core scope of work. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Foundation | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PART |
Dave Hannah
|
|
|
Weekly job walk. ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 7/16/2013 | 7/16/2013 | 7/16/2013 | P | PART |
Tom Arcoraci
|
|
|
Weekly inspection walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson no insp made
|
BLD-Conference | 7/8/2013 | 7/9/2013 | 7/9/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Inspection Request. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 7/1/2013 | 7/2/2013 | 7/2/2013 | A | PASS |
Dave Hannah
|
|
|
Need to inspect sheathing screws at 17th Floor. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/25/2013 | 6/26/2013 | 6/27/2013 | A | PASS |
Dave Hannah
|
|
|
17th floor sheetrock screw inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/24/2013 | 6/25/2013 | 6/25/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Inspection Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/17/2013 | 6/20/2013 | 6/21/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly job inspection. Adam ###-####. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 6/18/2013 | 6/18/2013 | 6/19/2013 | P | PART |
Dave Hannah
|
|
|
Weekly Inspection. Adam ###-#### >> Inspection requested via web by Adam Johnson 17 floor restroom ok to cover and second floor perimeter fire proofing ok
|
BLD-Conference | 6/17/2013 | 6/18/2013 | 6/19/2013 | A | CANC |
Dave Hannah
|
|
|
Weekly Inspection. Adam ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/7/2013 | 6/11/2013 | 6/12/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly inspection walk, framing, firestop, etc. Contact Adam ESI, John, FCS. Thank You. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 6/7/2013 | 6/10/2013 | 6/11/2013 | A | PART |
Dave Hannah
|
|
|
Document hand off of 1st and 3rd Floor Fire Duct Wrap and Support. Phone #: ###-#### >> Inspection requested via web by Adam Johnson I need hanging suport data
|
BLD-Conference | 6/3/2013 | 6/4/2013 | 6/4/2013 | A | PASS |
Dave Hannah
|
|
|
Weekly inspection walk. Forte Construction items, ADA countertop, and Catchup on 11th floor perimeter. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 5/31/2013 | 6/3/2013 | 6/4/2013 | A | PEND |
Dave Hannah
|
|
|
Scheduled inspection for 9:00 a.m. to meet with Jamal, Cabinet and Plumbing contractor to review restroom countertops. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 5/13/2013 | 5/14/2013 | 5/22/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Inspection Walk. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson see sign off book
|
BLD-Conference | 5/20/2013 | 5/21/2013 | 5/22/2013 | A | PART |
Dave Hannah
|
|
|
Weekly Job Inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson see sign off book
|
BLD-Conference | 5/3/2013 | 5/6/2013 | 5/6/2013 | A | PART |
Dave Hannah
|
|
|
Framing walk of 8th floor with FCS, and ESI. AKJ ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover 8th and 9th floor rest rooms and south stair tower
|
BLD-Conference | 4/19/2013 | 4/22/2013 | 4/22/2013 | A | PART |
Dave Hannah
|
|
|
Scheduled Inspection of Stair 1 : 1st Thru 5th Floors. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ( ok to sheetrock stair #1 basement thru floor 5 )
|
BLD-Framing/Rough-in | 4/10/2013 | 4/10/2013 | 4/17/2013 | A | PART |
Dave Hannah
|
|
|
|
BLD-Conference | 4/8/2013 | 4/9/2013 | 4/10/2013 | A | FAIL |
Dave Hannah
|
|
|
Weekly Inspection Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson c/n on site
|
BLD-Conference | 3/25/2013 | 3/26/2013 | 3/27/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly Inspection Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 3/12/2013 | 3/12/2013 | 3/21/2013 | P | PASS |
Dave Hannah
|
|
|
Weekly inspection, Shell and Core Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 3/19/2013 | 3/19/2013 | 3/21/2013 | A | PART |
Dave Hannah
|
|
|
Weekly inspection, Shell and Core Walk. Phone #: ###-#### >> Inspection requested via web by Adam Johnson. I walked project today no new framing to sign off
|
BLD-Conference | 3/19/2013 | 3/19/2013 | 3/21/2013 | P | CANC |
Dave Hannah
|
|
|
Phone #: 2084841503 >> Inspection requested via mobile web by Adam
|
BLD-Conference | 3/4/2013 | 3/5/2013 | 3/7/2013 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Adam Johnson walked project with Jenifer.
|
BLD-Conference | 2/27/2013 | 2/28/2013 | 3/1/2013 | P | PART |
Dave Hannah
|
|
|
Fireproofing Conference - 2:00 PM Phone #: ###-#### >> Inspection requested via web by Adam Johnson I had a meeting with contactors on inspections for fire proofing
|
BLD-Conference | 2/25/2013 | 2/26/2013 | 3/1/2013 | A | DONE |
Dave Hannah
|
|
|
Weekly site inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson attn weekly sub meeting schedule on track should start closing up walls in two weeks
|
BLD-Conference | 2/21/2013 | 2/21/2013 | 2/22/2013 | P | PART |
Dave Hannah
|
|
|
|
BLD-Conference | 2/20/2013 | 2/20/2013 | 2/20/2013 | A | PASS |
Dave Hannah
|
|
|
S/C weekly building inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 2/18/2013 | 2/19/2013 | 2/20/2013 | A | CANC |
Dave Hannah
|
|
|
S/C weekly building inspection. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 2/12/2013 | 2/12/2013 | 2/14/2013 | A | PEND |
Dave Hannah
|
|
|
8th and Main Inspection Walk. BP-1 Phone #: ###-#### >> Inspection requested via web by Adam Johnson still waiting on rough ins
|
BLD-Conference | 2/11/2013 | 2/12/2013 | 2/14/2013 | P | DONE |
Dave Hannah
|
|
|
8th and Main Inspection Walk. BP-1 Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 1/28/2013 | 1/29/2013 | 1/30/2013 | A | PART |
Dave Hannah
|
|
|
6th floor exterior framing, 3rd and 4th floor interior framing. Phone #: ###-#### >> Inspection requested via web by Adam Johnson all framing is ok but still needs other trades rough ins
|
BLD-Concrete | 1/2/2013 | 1/2/2013 | 1/3/2013 | P | PART |
Dave Hannah
|
|
|
5th Floor SOD Pre Placement Inspection. 8th and Main.
Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok aftetr mti sign off
|
BLD-Concrete | 12/17/2012 | 12/19/2012 | 12/28/2012 | A | PART |
Dave Hannah
|
|
|
4th Floor SOD inspection (2nd Placement) Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Concrete | 12/18/2012 | 12/18/2012 | 12/19/2012 | P | PASS |
Dave Hannah
|
|
|
4th Floor SOD inspection (1st Placement) Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Concrete | 12/17/2012 | 12/17/2012 | 12/18/2012 | P | DEFR |
Dave Hannah
|
|
|
4th Floor SOD inspection (1st Placement) Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Concrete | 12/12/2012 | 12/12/2012 | 12/12/2012 | A | PART |
Dave Hannah
|
|
|
3rd floor crews working on south half for placement tomorrow
|
BLD-Concrete | 12/6/2012 | 12/6/2012 | 12/6/2012 | P | PART |
Dave Hannah
|
|
|
second floor second pour and wall framing in basement
|
BLD-Concrete | 12/3/2012 | 12/3/2012 | 12/4/2012 | P | PART |
Dave Hannah
|
|
|
jamal Phone #: ###-#### walked project crews are getting ready to place concrete for second floor
|