BLD-Final | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Dave Hannah
|
|
|
Steve Phone #: ###-####
|
DOC - Permit Finaled | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Tony Young
|
|
|
Call when you are on your way- Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | DONE |
Mike Jordan
|
|
|
Barba Phone #: ###-####. Needs to insulate.
|
BLD-Framing/Rough-in | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. OK to insulate.
|
BLD-Conference | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | DONE |
Mike Jordan
|
|
|
Barbara Phone #: ###-####. Needs to provide truss engineering, install straps, roll block floor trusses at cantilever. Still need to inspect spiral stairs Also needs to complete MEP's and get rough in inspections before proceeding any further.
|
BLD-Aging Inspection | 12/20/2017 | 12/20/2017 | 12/21/2017 | | CANC |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 12/21/2017 | 12/21/2017 | 12/21/2017 | | PEND |
Mike Jordan
|
|
|
|
BLD-Conference | 8/8/2017 | 9/5/2017 | 9/5/2017 | A | DONE |
Mike Jordan
|
|
|
Check on progress. Trade permits have been issued.
|
BLD-Framing/Rough-in | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PART |
Mike Jordan
|
|
|
Barbara (alt. number Luke ###-####) Phone #: ###-####. Walk through only. Building has been framed and sided. No wall bracing inspection has been done. Noted that all blocking on the interior appeared to be installed. Portions of the addition are being used by the homeowner. Some plumbing has been completed and a laundry room and partial bathroom are being used. I noted to the homeowner that electrical, plumbing and mec. permits are required, get those permits have have the inspectors out to inspect work done this far. It appears that some electrical work has been completed. Homeowner using extension chords at this time for power. I contacted Daryl Degrange and Bill Vandegrift and made them aware of the situation. Home owner wants to complete work and sell house in one year. Will reschedule a building conferance in one month to check on progress.
|
BLD - Request for Extension | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | DONE |
Mike Jordan
|
|
|
Barbara Phone #: ###-####. Spoke with Barbara, they have framed the shell. I had her call for frsming inspection to see progress.
|
BLD - Resubmittal Approved | 5/20/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Jim Storey
|
|
|
Daniel// please call before Phone #: ###-#### 180 days
|
Extend Permit 90/180 days | 5/22/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Jim Storey
|
|
|
Daniel// please call before Phone #: ###-####
|
BLD-Conference | 3/21/2014 | 3/24/2014 | 3/24/2014 | A | DONE |
Mike Jordan
|
|
|
Call Kelly Temple with ada county asseors office for update. ###-####. Foundation only is completed at this time.
|
BLD-Conference | 3/21/2014 | 3/21/2014 | 3/21/2014 | P | CANC |
Mike Jordan
|
|
|
rescheduled for monday in the am.
|
BLD-Foundation | 11/7/2012 | 11/8/2012 | 11/8/2012 | P | PASS |
Jim Storey
|
|
|
Steve Baker Phone #: ###-####
|
BLD-Footing | 11/5/2012 | 11/6/2012 | 11/6/2012 | P | PASS |
Jim Storey
|
|
|
steve Phone #: ###-####
|