BLD-Final | 7/1/2013 | 7/1/2013 | 7/1/2013 | A | PASS |
Mike Jordan
|
|
|
Please call 1/2 hr prior Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Wall cover | 2/12/2013 | 2/12/2013 | 2/12/2013 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 2/12/2013 | 2/12/2013 | 2/12/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 2/11/2013 | 2/11/2013 | 2/11/2013 | A | PASS |
Mike Jordan
|
|
|
Please call 1/2hr prior Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 2/11/2013 | 2/11/2013 | 2/11/2013 | A | PASS |
Mike Jordan
|
|
|
Please call 1/2hr prior Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Framing/Rough-in | 2/7/2013 | 2/7/2013 | 2/7/2013 | P | PASS |
Mike Jordan
|
|
|
please call 1/2hr prior Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall cover | 12/18/2012 | 12/18/2012 | 12/18/2012 | P | PASS |
Mike Jordan
|
|
|
firewall Phone #: ###-#### >> Inspection requested via web by James Larkin. 3rd floor base layer of 5/8 type x.
|
BLD-Wall cover | 12/10/2012 | 12/10/2012 | 12/10/2012 | P | PASS |
Mike Jordan
|
|
|
Firewall Construction Phone #: ###-#### >> Inspection requested via web by James Larkin. 2nd floor face layers 5/8 type rock.
|
BLD-Wall cover | 12/7/2012 | 12/7/2012 | 12/7/2012 | P | PASS |
Mike Jordan
|
|
|
Firewall Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall cover | 12/6/2012 | 12/6/2012 | 12/6/2012 | A | PASS |
Mike Jordan
|
|
|
Firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin. 5/8 type x rock, face layer ok, 2nd. floor.
|
BLD-Wall cover | 12/4/2012 | 12/4/2012 | 12/4/2012 | P | PASS |
Mike Jordan
|
|
|
firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Conference | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Mike Jordan
|
|
|
Firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin. BAse and face layersmof 5/8 type x rock for 2hr fire wall. 1st.floor.
|
BLD-Footing | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-####. Interior footings.
|
BLD-Energy code compliance | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Rigid foam insulation on interior side of stemwal below slab on grade.
|
BLD-Foundation | 9/14/2012 | 9/18/2012 | 9/18/2012 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2085739589 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 9/14/2012 | 9/17/2012 | 9/17/2012 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2085739589 >> Inspection requested via mobile web by Ricardo
|