BLD-Final | 6/14/2013 | 6/14/2013 | 6/14/2013 | P | PASS |
Mike Jordan
|
|
|
Please call prior. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 6/14/2013 | 6/14/2013 | 6/14/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 3/13/2013 | 3/13/2013 | 3/13/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 2/25/2013 | 2/25/2013 | 2/25/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 2/22/2013 | 2/22/2013 | 2/22/2013 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Framing/Rough-in | 2/19/2013 | 2/20/2013 | 2/20/2013 | P | PASS |
Mike Jordan
|
|
|
Please call
Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 11/5/2012 | 11/5/2012 | 11/5/2012 | P | PASS |
Tom Arcoraci
|
|
|
Exterior Sheer Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 10/19/2012 | 10/19/2012 | 10/19/2012 | A | FAIL |
Mike Jordan
|
|
|
Exterior sheer Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall cover | 10/11/2012 | 10/11/2012 | 10/11/2012 | A | PASS |
Jim Sly
|
|
|
Firewall Construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall cover | 10/9/2012 | 10/9/2012 | 10/9/2012 | A | PART |
Jim Sly
|
|
|
Firewall construction 3rd level. Please call 1/2 hr prior. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin Insulation installed only.....OK
|
BLD-Wall Bracing | 10/1/2012 | 10/1/2012 | 10/1/2012 | P | PASS |
Tom Arcoraci
|
|
|
jim Phone #: ###-####
|
BLD-Wall Bracing | 9/28/2012 | 9/28/2012 | 9/28/2012 | A | PASS |
Mike Jordan
|
|
|
Firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 9/27/2012 | 9/27/2012 | 9/27/2012 | A | PART |
Mike Jordan
|
|
|
firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin. BAse and face layers for 2hr. firewall, both sides first floor.
|
BLD-Wall Bracing | 9/26/2012 | 9/26/2012 | 9/26/2012 | A | PART |
Mike Jordan
|
|
|
firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin. 2hr. firewall, base layer, one side only and R-13 insualtion installed.
|
BLD-Other | 9/25/2012 | 9/25/2012 | 9/25/2012 | P | DONE |
Mike Jordan
|
|
|
reveiw fire wall construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Footing | 9/17/2012 | 9/18/2012 | 9/18/2012 | A | PASS |
Mike Jordan
|
|
|
greg Phone #: ###-####. Interior thickend footings ok.
|
BLD-Energy code compliance | 9/11/2012 | 9/11/2012 | 9/11/2012 | P | PASS |
Mike Jordan
|
|
|
steve Phone #: ###-####. Rigid foam insulation on interior side of stemwall below slab on grade.
|
BLD-Foundation | 9/4/2012 | 9/6/2012 | 9/6/2012 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2085739589 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 9/4/2012 | 9/5/2012 | 9/5/2012 | P | PART |
Mike Jordan
|
|
|
Phone #: 2085739589 >> Inspection requested via mobile web by Ricardo
|