BLD-Final | 11/30/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Jim Sly
|
|
|
Kelley Phone #: ###-####
|
DOC - Permit Finaled | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 9/26/2012 | 9/26/2012 | 9/26/2012 | P | PASS |
Tony Young
|
|
|
Kelly Phone #: ###-####
|
BLD-Framing/Rough-in | 9/20/2012 | 9/24/2012 | 9/24/2012 | A | PASS |
Tony Young
|
|
|
Kelly Phone #: ###-####/// ok to insulate
|
BLD-Footing | 8/15/2012 | 8/15/2012 | 8/15/2012 | P | PART |
Tony Young
|
|
|
Kelly Phone #: ###-####,, new addition dug out
|
BLD-Footing | 7/26/2012 | 7/27/2012 | 7/27/2012 | A | DONE |
Tony Young
|
|
|
KELLY Phone #: ###-####
|
BLD-Footing | 7/25/2012 | 7/26/2012 | 7/27/2012 | A | DONE |
Tony Young
|
|
|
Kelly Phone #: ###-####
|
BLD-Conference | 7/23/2012 | 7/25/2012 | 7/26/2012 | P | PART |
Tony Young
|
|
|
kelly late if possible Phone #: ###-####,, ok to keep digging exterior,, will need to go under and pin some
|
BLD-Conference | 7/11/2012 | 7/12/2012 | 7/24/2012 | A | FAIL |
Tony Young
|
|
|
kelly late if possible Phone #: ###-####,, needs foundation on new part below grade,, other issues are the floor deck,,, ok to dig down around foundation
|
BLD-Conference | 7/10/2012 | 7/11/2012 | 7/12/2012 | P | FAIL |
Tony Young
|
|
|
kelly late if possible Phone #: ###-####,, need to have a plan reviewer and or 325 visit site,, addition that was put on with out inspection may need some modification to meet code,, ok to dig out underfloor to meet clearance,,, also need to verify if floor deck will meet code,, 3/4" underlayment was used
|