BLD-Final | 3/17/2013 | 3/18/2013 | 3/18/2013 | A | PASS |
Jim Storey
|
|
|
Please call with time to meet onsite. I have a copy of the mech. permit in hand and we can open open up a wall, if necessary, to verify framing. thx Phone #: ###-#### >> Inspection requested via web by Todd Weltner
|
FIRE-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety okayed pending max. occupant signage is posted per plan review and red-line annotations, night latch at the south exit door removed while on site.
|
BLD-Final | 3/14/2013 | 3/15/2013 | 3/15/2013 | P | FAIL |
Jim Storey
|
|
|
Todd Phone #: ###-#### need mech permit and insp/ need to verify header for framing insp/ maintane fire wall anc ceilling protection at exsust vents. c/n posted.
|
FIRE-Sprinkler Rough-in | 1/10/2013 | 1/10/2013 | 1/10/2013 | A | PART |
Forrest France
|
|
|
Fire sprinkler work above the hard lid ceilings okayed for cover- ref. notations on the approved plans.
|