BLD-Final | 5/22/2013 | 5/22/2013 | 5/22/2013 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ. al issues were resolved. Engineer has resolved non compliances on special inspection report.
|
BLD-Final | 4/15/2013 | 4/16/2013 | 4/16/2013 | A | PART |
Mike Jordan
|
|
|
Temp occ. granted at this time. Have received letter from sunrise engineering. Still waiting for final letter from special inspection agency (Terracon). I did speak to greg from terracon this morning regarding final letter and if their were any outstanding issues. Greg noted two out standing issues. 1st is regarding a high slump test, 28 day strength test met project spec and the 2nd. issue was a failing density test. Location of this test was not with in the building footprint or foundation system, but rather in the parking lot. Terracon has forwarded these issues to architect for their review. As soon as issues are resolved, will be ok for perm occ.
|
BLD-Final | 4/12/2013 | 4/15/2013 | 4/15/2013 | P | NR |
Mike Jordan
|
|
|
travis Phone #: ###-####. Provide approved plans, final letter from special inspection agency and engineer of record. Correction notice issued.
|
FIRE-Final Inspection | 4/11/2013 | 4/12/2013 | 4/12/2013 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|